CRAIG R. COURTNEY, APPELLANT,
v.
R.L. SCHMECKPEPER, INC., APPELLEE
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
A painter appeals dismissal of a breach of contract claim for lack of subject matter jurisdiction. The trial court ruled as a matter of law that the ambiguous contract was for painting only one house, resulting in damages under $5,000, thereby losing circuit court jurisdiction. The court reversed, finding the contract ambiguous and holding that contract interpretation should be submitted to a jury, not decided by the judge as a matter of law.
The court held that the contract was ambiguous as to the number of houses to be painted and the total contract price, and therefore the issue of contract interpretation should have been submitted to a jury as a question of fact, not decided by the trial court as a matter of law. Because the contract's meaning was ambiguous, the amount in controversy was a jury question, affecting subject matter jurisdiction.
[1] A trial court errs by entering a directed verdict on the issue of breach of contract when the determination of whether a breach occurred is dependent on the jury's interp…
[2] A plaintiff bears the burden of proving every material allegation of its complaint that is denied by the defendant, including the existence of damages.
Previewing 2 of 5 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.
Join FLexlaw to unlock all legal intelligence“Because of the contract is ambiguous, the issue should be submitted to a jury for resolution as a question of fact.”
Establishes the core holding that ambiguous contract interpretation is a jury question, not a matter of law.
Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.
Join FLexlaw to unlock all legal intelligenceCraig Courtney, a painter, entered into a written contract with R.L. Schmeckpeper, Inc., a builder, to provide painting services. The contract's print…
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Amount In Controversy cases and more on FLexlaw
LEHAN, Judge.
Plaintiff appeals from the trial court’s dismissal of the complaint for lack of subject matter jurisdiction. We reverse for the reason that in this breach of contract case the amount in controversy was a matter for the jury because the contract is ambiguous as to whether the amount contracted for exceeded $5,000.
Plaintiff, a painter, prepared a written agreement to provide painting services for defendant, a builder. The first page of the agreement was a printed form describing the type of interior and exterior painting to be done and stating that the work would be performed at “Kings Lake Model B.” The space for the contract price was filled in with the figure of $2,350.
Attached to the printed form were two pages of additional contract provisions, handwritten by plaintiff. Paragraph Seven of those provisions states “Pricing has been based on painting 49 houses Model A, B, or C or any combination of the three models totaling 49 houses. If less than 49 houses are painted, the painting cost per house will be negotiated upwards.” Several changes to the handwritten provisions had been made by defendant. In Paragraph Seven, the first “49” had been circled and the figure “20 ± ” had been inserted.
The contract was not performed, and plaintiff sued for its breach. The complaint alleged that the agreement was that plaintiff would be paid $2,350 per house for painting forty-nine houses, unless fewer than forty-nine houses were built, in which case the parties had agreed to negotiate a higher price per house.
Plaintiff began the trial by testifying on his own behalf. Plaintiff testified that he and defendant had agreed that plaintiff would paint the houses built by defendant in the Kings Lake development. According to plaintiff, at the time the contract was signed it was anticipated that defendant would build, and plaintiff would paint, forty-nine houses. Plaintiff testified that he based his price per house on the assumption that he would paint a large number of houses because he paid a lower price for the paint if he bought in lots large enough to paint ten houses.
During cross-examination of plaintiff, the trial court ruled as a matter of law that the face of the contract showed that it was for the painting of only one house with the pricing based on painting either forty-nine houses or “20 ±” houses. The court then ruled that it did not have jurisdiction because the possible damages were less than $5,000 and transferred the cause to county court.
On appeal, plaintiff contends that the issue of the correct interpretation of the contract should have been submitted to the jury. We agree. Because of our disposition of this first issue, we need not reach plaintiffs other point on appeal, which involves whether plaintiffs initial good faith demand in the complaint for damages exceeding $5,000 met the jurisdictional amount requirements in the circuit court notwithstanding developments at trial.
As to the first issue, in our view the written contract was ambiguous. The provisions of the contract relating to the number of houses to be painted are reasonably susceptible to more than one interpretation. The plaintiff testified that the contract was for more than one house. Paragraph Seven originally stated that pricing was based upon forty-nine houses, then was changed by defendant to read “20 ±” houses. Although the trial court stated that this provision pertained only to pricing and not to the number of houses contracted to be painted, it can be argued that it would be illogical to base a contract to paint one house upon the cost of painting forty-nine houses. In any event, an indication of the contract’s ambiguity is its statement in Paragraph Eight that “rooms in houses may be painted in pastel colors,” referring to more than one house.
Because the contract is ambiguous, the issue should be submitted to a jury for resolution as a question of fact. Hoffman v. Terry, 397 So. 2d 1184 (Fla. 3d DCA 1981). See Friedman v. Virginia Metal Products Corp., 56 So. 2d 515 (Fla.1952).
REVERSED AND REMANDED.
RYDER, A.C.J., and DANAHY, J., concur.
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By
-
Beaupre v. Casper Paul Testa, 449 So. 2d 311 (Fla. 2d DCA 1984)…80 (Fla.1983), holds section 627.7262 to be constitutional and not applicable to causes of action predicated on events occurring prior to the effective date of the statute. This court in Harris v. General Accident, Fire & Life Assurance Corp., Ltd., 442 So. 2d 294 (Fla. 2d DCA 1983), applied VanBibber to re [*312] verse the trial court’s dismissal of the ap-pellee insurance company as a party defendant. We are required by VanBibber and Harris to do likewise. Appellant also raises as error the failure of the…
Authorities Cited
- Arrow Prop. Ins. Adjusters, Inc. v. People's Tr. Ins. Co., 357 So. 3d 182 (Fla. 3d DCA 2024)
- Hoffman v. Terry, 397 So. 2d 1184 (Fla. 3d DCA 1981)