JAMES RIVER AND KANAWHA CANAL PARKS, INC., APPELLANT,
v.
RICHMOND METROPOLITAN AUTHORITY ET AL., APPELLEES

4th Cir. | 1973-08-17
No. 73-1841
Before HAYNSWORTH, Chief Judge, and FIELD and WIDENER, Circuit Judges.
481 F.2d 1280 United States Court of Appeals for the Fourth Circuit (1973) Negative Treatment
Cited by 9 cases

Opinion of the Court
PER CURIAM:

PER CURIAM:

Noting that no question concerning the standing of the parties or the jurisdiction of the court has been raised on appeal, we affirm on the opinion of the district court, 359 F.Supp. 611 (E.D.Va. 1973).

In the event a petition for certiorari be filed more than thirty days after the date of filing of this opinion, plaintiff is required to give bond with sufficient corporate surety, to be approved by the Clerk of this court, in the sum of $500,000, to hold the defendants, any or all of them, harmless on account of any increase in project construction costs or increase in interest rates on bonds sold to finance the project, either or both, which may occur because of delay occasioned on account of the filing of such petition for certiorari should the judgment of this court be affirmed.

Let the mandate of the court issue forthwith.

Affirmed.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

Previewing 3 of 9 citing cases — full citator treatment, depth of discussion, and citing context are member features.

Join FLexlaw to unlock all legal intelligence

Full citator, related cases, and AI research tools

Open in FLexlaw