NATURAL RESOURCES DEFENSE COUNCIL, INC., PROJECT ON CLEAN AIR, SAVE AMERICA'S VITAL ENVIRONMENT, INC., JANEY WEBER AND SUSANNE ALLSTROM, PETITIONERS,
v.
ENVIRONMENTAL PROTECTION AGENCY, RESPONDENT
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
The Fifth Circuit vacated and withdrew the portion of its prior opinion that was inconsistent with the Supreme Court's holding.
The Fifth Circuit previously held that Georgia's variance procedures were inconsistent with the Clean Air Act and that the EPA Administrator exceeded …
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Clean Air Act Amendments Of 1970 cases and more on FLexlaw
PER CURIAM.
In our earlier opinion rendered in this case, Natural Resources Defense Council, Inc. v. Environmental Protection Agency, 5 Cir. 1974, 489 F. 2d 390, we held, inter alia: “It was inconsistent with [the Clean Air Act Amendments of 1970, 42 U.S.C. §§ 1857 — 58a] for Georgia to adopt its own variance procedures, and that the Administrator exceeded his authority in approving [Ga.Code Ann. § 88-912].” Accordingly, in that opinion we directed the Administrator to publish forthwith his disapproval of Ga.Code Ann. § 88-912. 489 F. 2d at 403.
On certiorari, the United States Supreme Court reversed this portion of our opinion. Train v. Natural Resources Defense Council, Inc., 1975, 421 U.S. 60, 95 S.Ct. 1470, 43 L.Ed.2d 731. The Court held:
. [T]he Court of Appeals for the Fifth Circuit was in error when it concluded that the postponement provision of § 110(f) [43 U.S.C. § 1857c-5(f) is the sole method by which may be obtained specific ameliorative modifications of state implementation plans. The Agency had properly concluded that the revision mechanism of § 110(a)(3) [43 U.S.C. § 1857c-5(a)(3)] is available for the approval of those variances which do not compromise the basic statutory mandate that, with carefully circumscribed exceptions, the national primary ambient air standards be obtained is not more than three years, and maintained thereafter. 421 U.S. at 98, 95 S.Ct. at 1491, 44 L.Ed.2d at 757.
The portion of our earlier opinion inconsistent with this holding of the Supreme Court, reported as part III of our opinion, 489 F. 2d at 398 — 403, is therefore withdrawn and vacated.
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Authorities Cited
- Train v. Natural Res. Def. Council, Inc., 421 U.S. 60 (U.S. 1975)
- Natural Res. Def. Council, Inc. v. Env't Prot. Agency, 489 F.2d 390 (5th Cir. 1974)