CULLUM ELECTRIC & MECHANICAL, INC., APPELLANT,
v.
MECHANICAL CONTRACTORS ASSOCIATION OF SOUTH CAROLINA, APPELLEE

4th Cir. | 1978-02-02
No. 76-2074
569 F.2d 821 United States Court of Appeals for the Fourth Circuit (1978) Positive Treatment
Cited by 6 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.


Holding

The court held that the mechanical contractors' association's rule regarding the timing of subcontractor bids did not constitute an illegal price-fixing arrangement, group boycott, or discrimination against non-members under the Sherman Act.


Facts & Procedural History

A mechanical subcontractor sued, alleging violations of the Sherman Act after its bid was rejected. The rejection was based on a rule requiring subcon…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
HAYNSWORTH, Chief Judge:

HAYNSWORTH, Chief Judge:

These claims of a violation of Sections 1 and 2 of the Sherman Act arose out of the defendant’s insistence that general contractors submitting bids for the construction of a college library not use mechanical subcontractors’ bids submitted less than five hours before the deadline for submission of the general contractors’ bids, or less than four hours before the general contractors’ submission time if more than five hours before that time the subcontractor had filed his bid with Western Union. The arrangement was embodied in agreements entered into by the Mechanical Contractors Association and general contractors.1 The procedure was designed to avoid the chaotic situation resulting when general contractors received bids from subcontractors only minutes before the deadline for submission of the bids of general contractors, while guarding against the use of one subcontractor’s bid to prevail upon another to revise his bid to a still lower figure.

While once a member of the MCA, the plaintiff was not a member at the time of this bidding. It received no direct notice from the MCA that the five-hour rule was in effect on this job, but the district court found that it either knew or, upon inquiry, could have found that it was. Moreover, the procedures embodied in the agreement between the MCA and the general contractors applied equally to members and nonmembers of the MCA. If a member or non-member did not comply with the time requirements, the participating general contractors had obligated themselves not to use the bid.

The plaintiff filed its bid with the winning general contractor three hours and fifty-five minutes before the time for opening the bids of the general contractors; it had not filed a message containing the bid with Western Union. The bid of $422,-000.00 for the heating, air conditioning and electrical work was slightly less than $3,000.00 less than the next lowest combination of bids, but the successful general contractor did not use it, when the defendant insisted that its use would be in violation of the general contractors’ agreement.

In this appeal the plaintiff contests some of the factfinding by the district judge, but we find his findings, to the extent they have a material bearing upon the legal rights of the parties, supported by substantial evidence and not clearly erroneous. His conclusions that the procedures embodied in the agreements are not an arrangement to fix prices, nor to effect a group boycott, nor discriminatory against non-members of the MCA are clearly correct and appropriate as applied to the facts in this case.

The judgment is affirmed substantially for the reasons stated by the district court. Cullum Electric & Mechanical, Inc. v. Mechanical Contractors Association of South Carolina, 436 F.Supp. 418 (D.C.S.C.1976).

AFFIRMED.

. All but one of the general contractors submitting bids on this project had subscribed to the agreement. Importantly, the general contractor who got the job and who did not use the plaintiff’s bid was a signatory.


Cases With Similar Vibessemantic neighbors from the corpus

Full citator, related cases, and AI research tools

Open in FLexlaw