MISSISSIPPI POWER & LIGHT COMPANY, ET AL., PETITIONERS,
v.
FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT
MISSISSIPPI POWER & LIGHT COMPANY, ET AL., PETITIONERS,
FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT
736 F.2d 261
Court of Appeals for the Fifth Circuit (1984)
Opinion of the Court
PER CURIAM:
The Petitions for Rehearing are DENIED. See Fort Pierce Utility Authority of the City of Fort Pierce v. FERC, 736 F. 2d 214 (1984) (on rehearing). No member of this panel nor judge in regular active service on the court having requested that the court be polled on rehearing en banc (Federal Rules of Appellate Procedure and Local Rule 35), the Suggestion for Rehearing En Banc is DENIED.