ARVIDA CORPORATION, APPELLANT,
v.
SCOTT BARNETT AND SABRINA BARNETT, APPELLEES

Fla. 3d DCA | 1986-11-18
Nos. 85-2860, 86-473
Before BARKDULL, HENDRY and JORGENSON, JJ.
502 So. 2d 11 Florida District Court of Appeal, Third District (1986) Positive Treatment
Cited by 4 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.


Holding

A contract that limits a buyer's remedies for construction delays and makes specific performance available only to qualify for an ILSA exemption does not meet the statutory requirement for exemption.


Headnotes

[1] A seller is "obligated" to complete construction within two years for purposes of the Interstate Land Sales Full Disclosure Act exemption only if the contract contains an…

[2] A contract provision that limits a purchaser's remedies for a seller's default in construction to a refund of deposits, while prohibiting claims for damages or specific p…

Previewing 2 of 4 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Arvida failed to make required disclosures under the Interstate Land Sales Full Disclosure Act (ILSA). Arvida claimed an exemption under ILSA, asserti…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
HENDRY, Judge.

HENDRY, Judge.

Arvida Corporation (Arvida), a developer, appeals the entry of a final summary judgment for plaintiffs/appellees Scott and Sa brina Barnett (the Barnetts) granting the Barnetts rescission of their agreement to purchase a home from Arvida and ordering a refund of their deposits. Arvida also appeals the subsequent entry of an order taxing costs and attorney’s fees against it. We affirm the judgment and order under review based upon the following analysis.

The instant lawsuit was grounded in part upon Arvida’s failure to comply with certain disclosure requirements of the Interstate Land Sales Pull Disclosure Act, 15 U.S.C. §§ 1701-1720 (1982) (ILSA), which noncompliance entitles a purchaser to rescission. 15 U.S.C. § 1708(c). Arvida concedes it did not make the required disclosures. Its position both in the trial court and on appeal is that the instant transaction is exempt from ILSA pursuant to section 1702(a)(2).

Section 1702 provides in pertinent part: Exemptions

(a) Unless the method of disposition is adopted for the purpose of evasion of this chapter, the provisions of this chapter shall not apply to—

(2) the sale or lease of any improved land on which there is a residential, commercial, condominium, or industrial building, or the sale or lease of land under a contract obligating the seller or lessor to erect such a building thereon within a period of two years [.] (emphasis supplied).

The general rule is that a seller is “obligated,” within the meaning of section 1702(a)(2), only if the contract contains an unconditional commitment by the seller to complete construction within two years. Dorchester Development, Inc. v. Burk, 439 So. 2d 1032, 1035 (Fla. 3d DCA 1983). In Dorchester, condominium sales contracts gave purchasers the option to rescind if their units were not completed within two years. In rejecting the developer’s claim for exemption from ILSA’s disclosure requirements, we stated: “Where the seller is obligated to complete by a time certain, the purchaser is not limited, as here, to the remedy of rescission, but he may affirm the contract and seek damages.” Id. at 1034. Cf. Marco Bay Associates v. Vandewalle, 472 So. 2d 472 (Pla. 2d DCA 1985) (two year completion exemption applied where contract did not negate purchaser’s right to affirm the contract and seek damages or specific performance).

With respect to remedies, the Barnetts’ purchase agreement provides:

12. Default.

Except as stated below, my [the Bar-netts’] only remedy against you [Arvida] for your default is to obtain a refund of my deposits (without interest).... I will have no right of specific performance (except, anything to the contrary in this agreement notwithstanding, specific performance of the obligation to substantially complete the Unit as required in this agreement within the time period stated ... will be permitted if, but only if, specific performance of that obligation is an absolute condition for you to take advantage of the provisions of 15 U.S.C. § 1702(a)(2) ... under which this transaction is exempt from [ILSA])[.]

The same provision further prohibits the Barnetts from seeking damages in the event of Arvida’s default.

Arvida, while conceding that the exemption is not available if a contract directly or indirectly waives a buyer’s right to specific performance, argues that the effect of paragraph 12 is to specifically preserve that remedy rather than to negate it.

The trial court, however, found that Ar-vida cannot take advantage of the exemption because its contract with the Barnetts “limits the remedies available to a purchaser in the event the building is not constructed within two years.” Additionally, the trial court found that “it is apparent from the face of the contract that the qualified availability of specific performance is included solely for the purpose of evading the act in violation of 15 U.S.C. § 1702(a)(2).” Although we have carefully considered Arvida’s argument, it is patently clear from the plain language of paragraph 12 that the remedy of specific performance is made available to the Barnetts solely in order for Arvida to evade ILSA’s disclosure requirements. Section 1702(a) expressly prohibits such a method of disposition. Accordingly, and in light of the additional contractual limitation prohibiting the Bar-netts from seeking damages in the event of Arvida’s default, we conclude that the trial court correctly ruled as a matter of law that the instant agreement fails to meet the statutory requirement of a bona fide obligation to construct within two years.

All other points raised by Arvida have been considered and we conclude that no reversible error has been demonstrated. Therefore, and in the absence of any genuine issues of material fact, we affirm in all respects the summary judgment under review and the award of attorney’s fees and costs thereunder. Affirmed.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • Samara Dev. Corp. v. Marlow, 556 So. 2d 1097 (Fla. 1990)
    …its within two years, Dorchester is not exempt from the provision of the Act requiring that it furnish a property report to the purchasers in advance of the signing of the contract. Id. at 1035 (citations omitted). See also Arvida Corp. v. Barnett, 502 So. 2d 11 (Fla. 3d DCA 1986), review denied, 511 So. 2d 297 (Fla.1987); cf. Marco Bay Assocs. v. Vandewalle, 472 So. 2d 472 (Fla. 2d DCA 1985), review denied, 482 So. 2d 350 (Fla.1986). In Berzon v. Oriole Homes Corp., 497 So. 2d 670 (Fla. 4th DCA 1986), the…
  • Hamptons Dev. Corp. OF Dade v. Sackler, 522 So. 2d 1035 (Fla. 3d DCA 1988)
    …contain an unconditional commitment by the seller to complete the construction within a two-year period so as to bring the contract within the exemption set forth in Title 15, United States Code, Section 1702(a)(2). Compare Arvida Corp. v. Barnett, 502 So. 2d 11 (Fla. 3d DCA 1986), rev. denied, 511 So. 2d 297 (1987) (contractual limitation on legal remedy available to buyer makes illusory the seller’s obligation to complete the construction within two years; contract not exempt from disclosure requirements…