ELOISE LOCKHART, APPELLANT,
v.
RONALD WORSHAM, D/B/A WORSHAM CONSTRUCTION COMPANY, APPELLEE
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
A homeowner appealed a judgment in a construction contract dispute, arguing the trial court awarded insufficient damages for the contractor's breach. The appellate court reversed, holding that the contractor's failure to comply with specifications did not qualify for substantial performance doctrine, and remanded for calculation of damages based on the reasonable cost of correcting the defective work.
The trial court erred in applying the substantial performance doctrine because the contractor's variance from specifications was not inadvertent, unintentional, or unimportant. The appropriate measure of damages is the reasonable cost of making the work conform to the contract, not minimal damages based on a finding of non-willful breach.
[1] A contractor's good faith attempt to correct defects does not preclude a finding of breach of contract.
[2] A homeowner is entitled to damages for a contractor's failure to comply with contract specifications, even if the breach is not willful or intentional.
Previewing 2 of 6 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.
Join FLexlaw to unlock all legal intelligence“the measure of damages is the reasonable cost of making the work conform to the contract”
Establishes the proper damages measure for defective performance rather than minimal nominal damages
Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.
Join FLexlaw to unlock all legal intelligenceLockhart contracted with Worsham Construction for kitchen and porch remodeling and roof installation for $18,525. The contract specified kitchen cabin…
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Substantial Performance cases and more on FLexlaw
BOOTH, Chief Judge.
This cause is before us on appeal from a final judgment entered in a suit to recover the balance allegedly due on a contract and a counterclaim for damages due to breaches of the agreement. The trial court awarded the contractor $1,500, finding in pertinent part:
The plaintiff [contractor] attempted in good faith to correct items complained of by the defendant [Ms. Lockhart]. The plaintiff [contractor] did not willfully or intentionally breach the terms of the parties’ agreement.
There is sufficient evidence to support the trial court’s finding that the contractor breached the contract; however, we must reverse the final judgment because the trial court imposed the wrong remedy and awarded only minimal damages ($65.00) to the homeowner based on its finding that the breach was not willful or intentional.
The record reflects that the parties entered into a written contract providing, in part, that the contractor would remodel the kitchen and porch, and install a new insulated built-up roof on the home. The total price for the work was to be $18,525.
The homeowner paid all except $1,500,1 which she refused to pay because the work was not in compliance with the agreement and was unsatisfactory. Specifically at issue are the kitchen cabinets and the roof. The contract required cabinets to be 24 inches deep to accommodate the dishwasher in the kitchen. The contractor claims the cabinets were 24 inches deep; Ms. Lockhart claimed the cabinets measured 23 and one-half inches deep. Photographic exhibits of record reveal the depth of the cabinets caused the 24-inch-deep dishwasher to protrude, but the court only awarded $15 to cover the cost of cutting a piece out of a drawer to allow it to open despite the protruding dishwasher. The homeowner was entitled to a kitchen counter with the appliances flush as bargained for, and to the drawers functioning without cut-outs caused by the contractor’s failure to comply with specifications.
The contract called for an insulated five-ply roof, but the contractor installed a three-ply roof with no insulation board. There was no finding of waiver. The allowance of a credit for insulation board not used does not compensate the homeowner for the incorrect roof which was not as contracted for. Perhaps the trial court intended to apply the doctrine of substantial performance. However, that doctrine is applicable where a variance from the specifications of the contract is inadvertent or unintentional and unimportant so that the work actually performed is substantially what was called for in the contract. 17A C.J.S. Contracts § 509(b)p (1974). The evidence here does not support application of that doctrine. Therefore, the measure of damages is the reasonable cost of making the work conform to the contract. As stated in Volume 17 Florida Jurisprudence Second Damages Section 29 (1980): “Generally, where the performance of a contract is defective, the measure of damages is the reasonable cost of making the work performed or the article furnished conform to the contract.”
Accordingly, we reverse the judgment below and remand to the trial court for redetermination of damages in light of this opinion.
WENTWORTH and THOMPSON, JJ., concur. . This amount reflects the balance due after accounting for a $200 credit for the roof insulation admittedly not installed and $205 for exhaust connection. Both credits were agreed to by the contractor.
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By
-
In re Standard Jury Instructions-Contract & Bus. Cases, 116 So. 3d 284 (Fla. 2013)…rine of substantial performance applies when the variance from the contract specifications is inadvertent or unintentional and unimportant so that the work actually performed is substantially what was called for in the contract. Lockhart v. Worsham, 508 So. 2d 411, 412 (Fla. 1st DCA 1987). “In the context of contracts for construction, the doctrine of substantial performance is applicable only where the contractor has not willfully or materially breached the terms of his contract or has not intentionally fail…
-
Nat'l Constructors, Inc. v. Ellenberg, 681 So. 2d 791 (Fla. 3d DCA 1996)…e contractor has not willfully or materially breached the terms of his contract or has not intentionally failed to comply with the specifications. Lazovitz, Inc. v. Saxon Constr., Inc., 911 [*794] F. 2d 588, 592 (11th Cir.1990); Lockhart v. Worsham, 508 So. 2d 411, 412 (Fla. 1st DCA 1987) (“[The] doctrine [of substantial performance] is applicable where a variance from the specifications of the contract is inadvertent or unintentional and unimportant so that the work actually performed is substantially what w…
-
Sunhouse Constr., Inc. v. Amwest Sur. Ins. Co. & Consol. Techniques, Inc., 841 So. 2d 496 (Fla. 3d DCA 2003)…titled to the balance under the Subcontract, after taking into account the amount of money Sunhouse expended, CTI would recover nothing, and in fact, would owe money to Sunhouse for the costs of completion. Id. at 1212; see also Lockhart v. Worsham, 508 So. 2d 411 (Fla. 1st DCA 1987) (proper measure of damages is reasonable cost of making work conform to the contract); Vanater v. Tom Lilly Constr., 483 So. 2d 506, 508 (Fla. 4th DCA 1986) (court found that contractor was liable for the full cost of replacing p…
Previewing 3 of 6 citing cases — full citator treatment, depth of discussion, and citing context are member features.
Join FLexlaw to unlock all legal intelligence