ESSEX CRANE RENTAL CORPORATION OF ALABAMA, APPELLANT,
v.
MILLMAN CONSTRUCTION COMPANY, INC., AND FIDELITY AND DEPOSIT COMPANY OF MARYLAND, APPELLEES

Fla. 3d DCA | 1987-12-22
No. 87-607
Before SCHWARTZ, C.J., and BASKIN and DANIEL S. PEARSON, JJ.
516 So. 2d 1130 Florida District Court of Appeal, Third District (1987) Positive Treatment
Cited by 2 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.


Holding

The court held that the forty-five day notice period for a mechanic's lien payment bond begins upon delivery of materials to the job site, not when the materials are assembled and ready for use.


Headnotes

[1] The forty-five day period for serving notice to a contractor on a payment bond begins to run from the date of the first delivery of materials to the job site, even if the…

[2] Delivery of materials to the site of an improvement constitutes prima facie evidence of their incorporation into the improvement for purposes of mechanic's lien notice re…

Previewing 2 of 4 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

A construction crane's unassembled parts were delivered to a job site in July, and the crane was assembled and used in October. The owner of the crane…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
SCHWARTZ, Chief Judge.

SCHWARTZ, Chief Judge.

In an action by the owner of a large construction crane on a mechanic’s lien payment bond posted under section 713.23, Florida Statutes (1983), the trial court entered summary judgment for the defendants, the contractor and surety, on the ground that the notice to contractor required by section 713.23(l)(d)1 had not been timely served. In so doing, the court held that the forty-five day period for the notice in question began to run in July, 1983, when unassembled pieces of the crane were delivered to the job site, rather than in early October, 1983, when the crane had been assembled and both was ready for use and was in fact employed in the construction process. We agree and affirm.

In our view, this result is compelled by a common sense reading of the statutory language which pegs the commencement of the period at the point of “beginning to furnish labor, materials, or supplies....” [e.s.] It is supported also by that portion of section 713.01(6)2 which provides that “[t]he delivery of materials to the site of the improvement shall be prima facie evidence of incorporation of such materials in the improvement.” On the other hand, we think that Essex’s reliance on that portion of section 713.01(6) which refers to the supplying of machinery “to the extent of the reasonable rental value for the period of actual use” is misplaced; this portion of the admittedly difficult subsection appears, however murkily, to refer to the amount of payment protected under the mechanic’s lien law rather than to the notice issue before us. Since the first notice was not given until October 17, 1983, more than forty-five days after the July date of first delivery which we have determined is deemed to have set the notice clock running, we conclude that summary judgment was properly entered. See Oolite Indus., Inc. v. Millman Constr. Co., 501 So. 2d 655 (Fla. 3d DCA 1987) (forty-five day notice period runs from first fabrication of special materials even though later actually incorporated into improvement), review denied, 509 So. 2d 1118 (Fla.1987); see also Pilot Elec. Constr. Co. v. Waters, 384 So. 2d 61 (Fla. 1st DCA 1980) (forty-five day notice to owner provision begins from first commencement of work on project even though contractual arrangements were subsequently modified).

The lower court also awarded attorney’s fees for the successful defendants. Because, as the appellees forthrightly concede, no such fees are recoverable from a contractor like Millman, Julian E. Johnson & Sons, Inc. v. Balboa Ins. Co., 408 So. 2d 1044 (Fla.1982), and there is no other basis for recovery against the surety, see §§ 627.728(1), 627.756, Fla.Stat. (1988), this portion of the judgment under review is set aside.

Affirmed in part, reversed in part.

. Section 713.23(l)(d) provides:

(d) Either before beginning or within 45 days after beginning to furnish labor, materials, or supplies, a lienor who is not in privity with the contractor, except a laborer, shall serve the contractor with notice in writing that the lienor will look to the contractor’s bond for protection on the work. If a notice of commencement is not recorded, or a reference to the bond is not given in the notice of commencement, and in either case if the lien-or not in privity with the contractor is not otherwise notified in writing of the existence of the bond, the lienor not in privity with the contractor shall have 45 days from the date the lienor is notified of the existence of the bond within which to serve the notice. The notice may be in substantially the following form:

NOTICE TO CONTRACTOR

To . (name of contractor). The undersigned notifies you that he has furnished or is furnishing.(services or materials) .... for the improvement of the real property identified as.(property description) . owned by . (owner’s name

and address) .under an order given by . and that the undersigned will look to the contractor’s bond for protection on the work.

.(Lienor’s signature and address).

. 713.01. Definitions

As used in this part:

(6) Furnish materials means supply materials which are incorporated in the improvement including normal wastage in construction operations; or specially fabricated materials for incorporation in the improvement; or supply materials used for the construction and not remaining in the improvement, subject to diminution by the salvage value of such materials; and includes supplying tools, appliances or machinery used on the particular improvement to the extent of the reasonable rental value for the period of actual use (not determinable by the contract for rental unless the owner is a party thereto), but does not include supplying hand tools. The delivery of materials to the site of the improvement shall be prima facie evidence of incorporation of such materials in the improvement.

Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • Stunkel v. Gazebo Landscaping Design, Inc., 660 So. 2d 623 (Fla. 1995)
    …& Plastering v. Tetor, 582 So. 2d 15, 17 (Fla. 2d DCA) (forty-five-day period ran from the day the services and materials were delivered to the job site), review dismissed, 587 So. 2d 1329 (Fla.1991); Essex Crane Rental Corp. v. Millman Constr. Co., 516 So. 2d 1130, 1131 (Fla. 3d DCA 1987) (forty-five-day period ran from when unassembled parts were furnished to a job site, not when the parts were assembled into a working crane several months later), review denied, 525 So. 2d 878 (Fla.1988); Daly Aluminum Prods…