We reverse the trial court’s order granting Robert B. Carpenter’s (Carpenter) motion to vacate default judgment.
A defaulting party may vacate a default judgment if the defaulting party proves excusable neglect, a meritorious defense, and a showing of due diligence in seeking relief after learning of the default. Schneiderman v. Cantor, 546 So. 2d 51 (Fla. 4th DCA 1989). In the instant case, Carpenter failed to exercise due diligence in seeking relief. Forty-eight days passed before Carpenter took any action after learning of the default. Moreover, he of fered no reasonable explanation for the forty-eight day delay. See Fischer v. Barnett Bank of South Florida, N.A., 511 So. 2d 1087 (Fla. 3d DCA 1987); Bayview Towers Condo. Assoc., Inc. v. Schweitzer, 475 So. 2d 982 (Fla. 3d DCA 1985) and Westinghouse Credit Corp. v. Steve Lake Masonry, Inc., 356 So. 2d 1329 (Fla. 4th DCA 1978).
DOWNEY and POLEN, JJ„ concur.
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By
-
Morton L. Ginsberg & MLG Props., Inc. v. Lennar Fla. Holdings, 645 So. 2d 490 (Fla. 3d DCA 1994)…default due to excusable neglect in answering Lennar’s amended complaint. See and compare Fla.R.Civ.P. 1.540(b); Otero v. G.I.E. Ins. Co., 606 So. 2d 443 (Fla. 2d DCA 1992), review denied, 614 So. 2d 502 (Fla.1993); World’s Finest Inc. v. Carpenter, 564 So. 2d 626 (Fla. 4th DCA 1990); Techvend Inc. v. Phoenix Network Inc., 564 So. 2d 1145 (Fla. 3d DCA 1990); Fischer v. Barnett Banks, 511 So. 2d 1087 (Fla. 3d DCA 1987); Bayview Tower Condominium v. Schweizer, 475 So. 2d 982 (Fla. 3d DCA 1985); Lacore v. Girald…
-
Apolaro v. Falcon, 566 So. 2d 815 (Fla. 3d DCA 1990)…ircumstances presented. See Edwards v. City of Fort Walton Beach, 271 So. 2d 136, 137 (Fla.1972). The court must evaluate, in other words, not only the amount of the delay but the reason for the delay. See World’s Finest Products, Inc. v. Carpenter, 564 So. 2d 626, 627 (Fla. 4th DCA Aug. 1, 1990). In Bay-view, unlike the present case, there was no prompt request to counsel for consent to vacate the default and, unlike the present case, there was no explanation for Bay-view’s thirty-day delay in filing the mot…
-
Paleias v. Wang, 632 So. 2d 1132 (Fla. 4th DCA 1994)…ue diligence in moving to set aside the default where 100 days had elapsed after receipt of the unilateral pretrial stipulation indicating a default had been entered, with no reason offered for the delay.5 World’s Finest Products, Inc. v. Carpenter, 564 So. 2d 626 (Fla. 4th DCA 1990); Techvend, Inc. v. Phoenix Network, Inc., 564 So. 2d 1145 (Fla. 3d DCA 1990); Fischer v. Barnett Bank of South Florida, N.A., 511 So. 2d 1087 (Fla. 3d DCA 1987); Bayview Tower Condominium Ass’n. v. Schweizer, 475 So. 2d 982 (Fla.…
Previewing 3 of 6 citing cases — full citator treatment, depth of discussion, and citing context are member features.
Join FLexlaw to unlock all legal intelligenceAuthorities Cited
- State v. Camper, 356 So. 2d 1329 (Fla. 4th DCA 1978)
- Westinghouse Credit Corp. v. Steven Lake Masonry, Inc., 356 So. 2d 1329 (Fla. 4th DCA 1978)
- Bayview Tower Condo. Ass'n, Inc. v. Schweizer, 475 So. 2d 982 (Fla. 3d DCA 1985)
- Hubert Fischer & Angeles de Fischer v. Barnett Bank OF S. Fla., N.A., 511 So. 2d 1087 (Fla. 3d DCA 1987)
- Schneiderman v. Cantor, 546 So. 2d 51 (Fla. 4th DCA 1989)