MONROE COUNTY, PETITIONER,
v.
HEMISPHERE EQUITY REALTY, INC., ET AL., RESPONDENTS

Fla. 3d DCA | 1993-02-02
No. 92-1793
Before SCHWARTZ, C.J., and FERGUSON and LEVY, JJ.
613 So. 2d 550 Florida District Court of Appeal, Third District (1993) Positive Treatment
Cited by 2 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.


Holding

The court held that a building permit expired under the terms of the zoning code because the developer failed to complete the project within the specified time after plan approval.


Facts & Procedural History

A county board affirmed a planning commission's decision that a developer's building permit had expired. The developer had not completed the project w…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.

Opinion of the Court
SCHWARTZ, Chief Judge.

SCHWARTZ, Chief Judge.

We conclude that the circuit court departed from the essential requirements of the law in quashing a resolution of the Monroe County Board of County Commissioners. The resolution affirmed a decision of the Monroe County Planning Commission that the respondent-developer’s building permit had expired under the terms of the “old” Monroe County Zoning Code Section 6-226(a)1 as incorporated into Section 9.5-2(b)(l)a2 of the “new” code. It is apparent that, as a matter of law, the board and the commission correctly decided that the respondents’ admitted failure to complete the project within two years after its development plan was approved resulted in the termination of the permit. See Peters v. Thompson, 68 So. 2d 581 (Fla.1953); 7 Fla.Jur.2d, Building, Zoning, and Land Controls § 134 (1978).

Accordingly, certiorari is granted, the final judgment below is quashed, and the cause is remanded with directions to affirm the resolution, and for further appropriate proceedings as to counts two and three which remain pending before the circuit court.

Certiorari granted.

. This provision stated:

In addition ... all proposed major development projects shall be subject to the following performance standards:
(a) Construction of all major development projects shall be initiated within one (1) year and completed within two (2) years after approval of the final development plan unless otherwise specified or approved by the zoning board.

. This subsection provides:

a. The holder of a final major development approval granted prior to the effective date of the Monroe County Comprehensive Plan and this chapter shall be entitled to develop pursuant to the approved final major development approval, (emphasis supplied).

Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • Monroe Cnty. v. Hemisphere Equity Realty, Inc., 634 So. 2d 745 (Fla. 3d DCA 1994)
    …board and the commission correctly decided that the respondents’ admitted failure to complete the project within two years after its development plan was approved resulted in the termination of the permit.” Monroe County v. Hemisphere Equity Realty, 613 So. 2d 550 (Fla. 3d DCA 1993). This court then remanded “for further appropriate proceedings” as to the remaining count — that the County was equitably estopped from enforcing the two-year build-out provision.2 The trial court, following a bench trial, issued…