Synopsis

Montesino sought arbitration of breach of contract claims against his former employers and their principal, but the trial court stayed arbitration, finding the defendants were not proper parties to the arbitration agreements. The appellate court reversed, holding that questions about whether parties are bound by arbitration agreements due to subsequent events must be determined by arbitrators, not trial courts.


Holding

A trial court may not stay or enjoin arbitration based on disputes over whether parties are bound by arbitration agreements due to events occurring after the contract was made; such issues must be resolved by the arbitrators themselves.


Headnotes

[1] A trial court may not enjoin or stay an arbitration proceeding based on factual matters occurring after the contract's formation that allegedly render the contract invali…

[2] A trial court's jurisdiction to determine issues related to arbitration is limited to whether parties have waived their contractual right to arbitration through subsequen…

Previewing 2 of 3 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Key Quotes

“the circuit court may not enjoin or stay an arbitration proceeding upon the ground that the contract providing for arbitration is not in force and effect because of factual matters which may have occurred since the making of the contract. Such an issue is an issue for the arbitrators.”

Establishes the core holding that disputes over contract validity based on post-contract events must be resolved by arbitrators, not trial courts.

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Montesino had employment contracts with Advent Technologies, Medtek Technologies, and Martin Swarzman, each containing dispute resolution clauses requ…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
PER CURIAM.

PER CURIAM.

The underlying dispute stems from a series of employment contracts between Rincci Montesino and at least one of the following parties: Advent Technologies, Inc. [Advent], Medtek Technologies, Inc. [Medtek], and Martin Swarzman. Montesino filed a demand for arbitration, pursuant to the dispute resolution clause contained in each of the agreements, alleging breach of contract against Advent, Medtek, and Swarzman. In turn, Advent, Medtek, and Swarzman filed a motion in circuit court to stay arbitration and for permanent injunction, pursuant to section 682.03(4), Florida Statutes (1995). After a summary hearing, the circuit court granted the motion to stay arbitration and for permanent injunction as to Advent and Swarzman, and partially granted the motion as to Med-tek by allowing arbitration to proceed solely as to the last employment agreement. Mon-tesino appeals from this order. We reverse.

A review of the record reveals that the validity of the arbitration clause itself was not attacked below, but rather, that the main issues before the trial court were whether Advent, Medtek, and Swarzman were proper parties to the arbitration and if so, pursuant to which contract. Advent, Medtek, and Swarzman argue that by extension of the holding in Florida Education Association v. Sachs, 650 So. 2d 29 (Fla.1995), the trial court was vested with jurisdiction to make this determination. We disagree.

We believe that the Sachs ease should be limited to its narrow holding that “a trial court may determine whether parties to an arbitration agreement have, by their subsequent conduct, waived their contractual right to arbitration.” Sachs, 650 So. 2d at 30. Consequently, since this ease does not involve the waiver of arbitration by subsequent acts, we rely on Gersh v. Concept House, Inc., 291 So. 2d 258 (Fla. 3d DCA 1974), where we have previously held that:

[T]he circuit court may not enjoin or stay an arbitration proceeding upon the ground that the contract providing for arbitration is not in force and effect because of factual matters which may have occurred since the making of the contract. Such an issue is an issue for the arbitrators. We are convinced that a contrary determination would frustrate the purposes of arbitration by furnishing a means for delay resulting in destruction of the remedy provided in the contract and approved by the statute.

Gersh, 291 So. 2d at 259. See also, Medident Constr., Inc. v. Chappell, 632 So. 2d 194, 195 (Fla. 3d DCA 1994)(‘Where fraud or some other ground for avoidance or invalidity of contract is alleged as to an entire agreement rather than specifically as to the arbitration clause contained within the agreement, the entire matter should be resolved by arbitration.”).

Therefore, in the instant case, where Advent, Medtek, and Swarzman argue that some, if not all of them, are not proper parties to the arbitration because subsequent events revoked one or more of the prior employment agreements with Montesino, we find that these issues are properly left for resolution by the arbitrators. Because we find that the trial court improperly made these determinations, we reverse and remand to the trial court with directions for entry of an order directing the parties to proceed to arbitration.

Reversed and remanded with directions.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • …her Sound Country Club, Inc. v. Barber, 567 So. 2d 10 (Fla. 2d DCA 1990) (holding that when party admitted execution of contract but argued that contract had expired by its own terms, the issue was for arbitration); Montesino v. Advent Techs., Inc., 676 So. 2d 32 (Fla. 3d DCA 1996) (holding that whether subsequent events revoked employment agreements was issue properly left to arbitration). Thus, if the parties had a valid arbitration agreement, the question of its termination is for the arbitrators, not the…
  • …e v. Amica Mut. Ins. Co., 533 So. 2d 279 (Fla.1988); Blackhawk Heating & Plumbing Co. v. Data Lease Fin. Corp., 302 So. 2d 404 (Fla.1974); Medident Constr., Inc. v. Chappell, 632 So. 2d 194 (Fla. 3d DCA 1994); Montesino v. Advent Technologies, Inc., 676 So. 2d 32 (Fla. 3d DCA 1996), review denied, 684 So. 2d 1350 (Fla.1996); Public Health Trust v. M.R. Harrison Constr. Corp., 415 So. 2d 756 (Fla 3d DCA 1982), pet. for review denied, 427 So. 2d 737 (Fla.1983); Hirschfeld v. Crescent Heights, X, Inc., 707 So.…