BONEH, INC., ETC., APPELLANT,
v.
THOMAS F. DALY, APPELLEE

Fla. 3d DCA | 1999-07-14
No. 98-2259
Before JORGENSON, GERSTEN, and GODERICH, JJ.
743 So. 2d 542 Florida District Court of Appeal, Third District (1999)

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

Boneh, Inc., a drywall subcontractor, sought to recover from Thomas Daley, the personal guarantor of a promissory note, after the general contractor defaulted. The court affirmed judgment for Daley, holding that Boneh's release of its mechanic's lien and failure to refile it after entering a new agreement with the successor contractor without Daley's consent released the guarantor from liability.


Holding

The guarantor was released from liability because Boneh failed to properly preserve the collateral by waiving its lien and failing to refile it after the successor contractor defaulted. The creditor has an obligation not to deal with the debtor or security for the debt in a manner that harms the guarantor's interests.


Headnotes

[1] A personal guarantor is released from liability when the creditor enters into a new agreement with the debtor that alters the underlying obligation without the guarantor'…

[2] A creditor's failure to preserve collateral, to the detriment of a guarantor, can justify the release of the guarantor to the extent of the damage caused by the loss of c…

Previewing 2 of 4 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Key Quotes

“Failure to properly preserve the collateral justifies a release of the guarantor to the extent that he was damaged by the loss of the collateral.”

Establishes the governing legal principle that a creditor's failure to preserve collateral releases the guarantor from liability.

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Boneh contracted as a drywall subcontractor with G-Site, the general contractor, and obtained a promissory note personally guaranteed by Thomas Daley,…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
PER CURIAM.

PER CURIAM.

Boneh, Inc., appeals from a final judgment entered in favor of a personal guarantor. We affirm.

Boneh, Inc., a subcontractor, is a drywall installer that contracted to install drywall in a series of homes; G-Site was the general contractor. Thomas Daley was the president of G-Site’s corporate general partner. In January, 1995, G-Site executed a promissory note in favor of Boneh; the note was personally guaranteed by Thomas Daley. Boneh filed a claim of lien on the project three months later, in April, 1995.

On April 12, 1995, Boneh and Construction Consultants of Aventura, the successor general contractor, executed a letter agreement that reduced the price of the drywall subcontract to $57,500.00 to be paid in twelve monthly installments.

Pursuant to that letter agreement, Boneh waived, released, and relinquished any liens it had against the project. Boneh agreed to this relinquishment of liens and the reduced price in order to secure the continuation of its construction contract on the site with the successor general contractor. No new guarantee was executed; the guarantor, Thomas F. Daley, did not consent to the new agreement.

However, Boneh reserved its ability to refile a claim of lien in the event of nonpayment. Despite the new general contractor’s failure to pay, Boneh did not refile its lien.1

Boneh sued Daley, as personal guarantor, for failure to pay under the promissory note that G-Sites, the original general contractor, signed. Daley had signed the note as president of G-Site; the total amount claimed was $167,768.00. The complaint was amended to allege an action on a personal guarantee by Daley. Following a bench trial, the court entered final judgment for Daley, the guarantor. Boneh appeals.

We affirm, as the personal guarantor was released from any continuing liability once Boneh had entered into a new agreement with the successor general contractor, and had failed to protect the collateral by refiling a claim of lien. “Failure to properly preserve the collateral justifies a release of the guarantor to the extent that he was damaged by the loss of the collateral.” Baitcher v. National Indus. Bank of Miami, 368 So. 2d 439 (Fla. 3d DCA 1979).

See also Capital Bank v. Engar, 545 So. 2d 317 (Fla. 3d DCA 1989) (holding that where bank had restructured corporate debt without the consent of the guarantor, to the detriment of the guarantor, the guarantor was released from the guarantee); Dorsy v. Maryland Nat’l Bank, 334 So. 2d 273, 274 (Fla. 3d DCA 1976) (holding that “the law imposes on the creditor an obligation not to deal with the debtor or any security for the debt in such a manner as to harm the interest of the guarantor.”); compare with Dunser v. Southeast First Nat’l Bank of Miami 367 So. 2d 1094, 1096 (Fla. 3d DCA 1979) (holding that “under an absolute and unconditional contract of guaranty ... it is no defense that the creditor has lost security or has been negligent in regard to the protection of the collateral.”)2 In this case, Boneh, in order to remain on the project under the successor general contractor, waived and relinquished all hens it had on the property. Boneh’s failure to refile its lien once the successor contractor defaulted impaired the collateral to the guarantor’s detriment. The underlying agreement was altered and the hens were relinquished without the guarantor’s consent. The guarantor did not waive the maker’s duty to preserve the collateral. Boneh lost its lien against the property, thus failing to protect the collateral, and releasing the guarantor.3

AFFIRMED.

. The original general contractor, G-Sites, filed for bankruptcy. In the bankruptcy action, G-Site disputed Boneh's claim.

. We disagree with the trial court that there is an intradistrict conflict between Dunser and Baitcher. The terms of the underlying guarantees in each case were completely different, and were dispositive of the guarantor's continuing liability.

. We do not mean to suggest that the subcontractor had any statutory duty to refile the lien; its failure to do so, however, breached its duty to the guarantor.