CHARLES I. COX AND PATTI C. MCCANN, APPELLANTS,
v.
REED'S SWIMMING POOLS AND SERVICE, INC., APPELLEE

Fla. 2d DCA | 2000-03-01
No. 2D99-998
PATTERSON, C.J. and WHATLEY, J., Concur.
756 So. 2d 141 Florida District Court of Appeal, Second District (2000)

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.


Holding

The court held that the trial court correctly determined the appellee was a direct contractor entitled to enforce its lien, but erred in granting summary judgment on the amounts due without resolving factual disputes regarding performance.


Facts & Procedural History

Appellants contracted with a general contractor for a home and separately with appellee for pool construction. Appellee filed a construction lien, and…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
CAMPBELL, Judge.

CAMPBELL, Judge.

Appellants, Charles I. Cox and Patti C. McCann, challenge a final summary judgment entered in favor of appellee, Reed’s Swimming Pools & Service, Inc. We affirm in part and reverse in part.

Appellants owned residential property on which they contracted with a general contractor (Ken Franklin Homes) for a home to be built. Appellee contracted separately with appellants to construct a pool, spa, pool deck and screen enclosure for the home. Appellee filed a construction lien on appellants’ property to secure payment for the work appellee performed.

Appellants sued Ken Franklin Homes and appellee for breach of contract, recission of contract and to discharge an improper construction lien. The general contractor, Ken Franklin Homes, is not a party to this appeal. Appellee counterclaimed against appellants to foreclose its lien. The trial judge entered summary judgment for appellee determining that appellee was a direct contractor with appellants and not a subcontractor to the general contractor and was entitled to enforce its lien for the amounts due under the pool contract. We affirm that portion of the summary judgment.

Appellee conceded at oral argument that there are factual issues remaining as to whether the pool contract was completely performed as required. Those remaining factual disputes involve the heater connections for the spa, the absence of recessed planters in the pool decking, and the dimensions of the pool decking. We reverse the summary judgment insofar as it determined the amounts due appellee under its contract with appellant. On remand, the disputed factual issues should be resolved and appellants afforded setoffs against the contract amount for any unperformed work required of appellee that was not excused by appellants.

Affirmed in part, reversed in part and remanded.

PATTERSON, C.J. and WHATLEY, J., Concur.