J.J. GUMBERG CO., A DELAWARE CORPORATION, APPELLANT,
v.
JANIS SERVICES, INC., A FLORIDA CORPORATION, AND COLONIA INSURANCE COMPANY, A DELAWARE CORPORATION, APPELLEES

Fla. 4th DCA | 2003-05-28
No. 4D02-1953
STEVENSON and HAZOURI, JJ., concur., MAY, J., concurs in result only.
847 So. 2d 1048 Florida District Court of Appeal, Fourth District (2003) Positive Treatment
Cited by 28 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.


Holding

The court held that breach of contract claims were barred by the statute of limitations, but a declaratory judgment action seeking insurance coverage was timely filed.


Headnotes

[1] The statute of limitations for a breach of contract action begins to run when the last element constituting the cause of action occurs.

[2] A cause of action for breach of contract accrues when a valid contract, a material breach, and damages all exist.

Previewing 2 of 4 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

An employee of a contractor was injured at a mall owned by Gumberg and sued Gumberg. Gumberg filed a third-party complaint against the contractor, Jan…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
PER CURIAM.

PER CURIAM.

Appellant, J.J. Gumberg Co. (Gumberg), appeals from the dismissal -with prejudice of the complaint it filed against appellee, Janis Services, Inc. (Janis), in October 2001. We affirm in part and reverse in part.

In May 1994, Jams entered into a construction contract to remodel the food court at the Coral Ridge Mall which was maintained and operated by Gumberg. On June 29,1994, an employee of Janis, Samuel Green, was injured while working at the Mall. Green filed suit against Gumberg in case number 97-12195 and Gumberg filed a third party complaint containing three counts against Janis. Count I was for contractual indemnity, Count II was for contribution, and Count III was for common law indemnity. Upon Janis’s motion to dismiss, Counts II and III were dismissed with prejudice and the remaining count, alleging contractual indemnity, was set for trial in January 2001.

Shortly before trial, Gumberg filed a motion for leave to amend its third party complaint to amend its claim for contractual indemnity and add two claims for breach of contract, and one for declaratory relief. The trial court denied the motion to amend. Gumberg settled with Green and the trial court entered a partial order of dismissal. Gumberg renewed its motion to amend which the trial court denied. The contractual indemnity suit against Janis remains pending.

In October 2001, Gumberg filed a new complaint against Janis and Colonia Insurance Company, Janis’s insurance company. There were two counts against Janis for breach of the construction contract and one count for declaratory relief against Janis and Colonia. These counts were essentially the same as three of the counts proposed in Gumberg’s motion to amend in case number 97-12195. This new cause, case number 01-17838, was transferred to the trial judge presiding over case number 97-12195.

Janis then filed a motion to dismiss Gumberg’s new complaint arguing that each claim was barred by the statute of limitations1 and further that the claims should be dismissed for improper splitting of causes of action. The trial court granted the motion to dismiss with prejudice as to all three counts without stating the grounds for its dismissal.

The two claims for breach of contract are based upon Gumberg’s allegations that Janis breached the provisions of the contract requiring Janis to obtain liability insurance and to keep the construction area clean and follow safety precautions. In Abbott Lab., Inc. v. Gen. Elec. Capital, 765 So. 2d 737, 740 (Fla. 5th DCA 2000), the court held that “[ujnder section 95.11(2)(b), the limitations period begins to run when ‘the last element constituting the cause of action occurs.’ § 95.031(1), Fla. Stat. (1997). The elements of a breach of contract action are: (1) a valid contract; (2) a material breach; and (3) damages.” Assuming that Janis breached the contract by failing to obtain liability insurance and by failing to clean up and maintain safety precautions at the time Green was injured in June of 1994, all the elements for a cause of action for breach of contract existed. Therefore, the trial court correctly dismissed these two claims as they are barred by the statute of limitations.

In the third count, Gumberg brought a declaratory judgment action against Janis and Colonia asking the trial court to determine the rights of Gumberg under the insurance policy issued to Janis. The issues for determination are whether Gumberg was an additional insured under the policy at the time of Green’s accident and whether Gumberg was entitled to coverage and a defense from Colonia. In this claim, the contract at issue is the insurance contract between Janis and Colonia. “In regard to insurance contracts, a specific refusal to pay a claim is the breach which triggers the cause of action and begins the statute of limitations running.” Donovan v. State Farm Fire and Cas. Co., 574 So. 2d 285, 286 (Fla. 2d DCA 1991). When Gum-berg settled Green’s negligence action in January 2001, the issue of coverage under the insurance policy became ripe for determination. Therefore, this declaratory judgment action was filed well within the statute of limitations.

Janis further argues that this claim was properly dismissed because there was an improper splitting of a cause of action. This rule is inapplicable here because Gumberg has not previously filed any action on Gumberg’s right to insurance coverage under Janis’s insurance policy purchased through Colonia.

Although the statute of limitations has run on Gumberg’s claims for breach of contract between Gumberg and Janis, this does not preclude the declaratory judgment action for a determination as to whether coverage exists for Gumberg under the policy of insurance purchased by Janis from Colonia. The declaratory judgment action will determine whether there is coverage for Gumberg. It is unclear why Gumberg chose to make Janis a party to the declaratory judgment action but that issue is not before us.

Based upon the foregoing, we affirm the trial court’s dismissal of the two causes of action for breach of contract. We reverse the dismissal of the declaratory judgment action and remand for further proceedings.

AFFIRMED in part; REVERSED in part.

STEVENSON and HAZOURI, JJ., concur. MAY, J., concurs in result only.

. Section 95.11(2)(b), Florida Statutes (1994), provides:

Actions other than for recovery of real property shall be commenced as follows:
(2) Within five years.—

(b) A legal or equitable action on a contract, obligation, or liability founded on a written instrument.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By (21 total)

  • Friedman v. NEW York Life Ins. Co., 985 So. 2d 56 (Fla. 4th DCA 2008)
    …s policy, indicating how each violates a part of the Florida Insurance Code. An adequately pled breach of contract action requires three elements: (1) a valid contract; (2) a material breach; and (3) damages. J.J. Gumberg Co. v. Janis Servs., Inc., 847 So. 2d 1048, 1049 (Fla. 4th DCA 2003); Indus. Med. Pub. Co. v. Colonial Press of Miami, Inc., 181 So. 2d 19, 20 (Fla. 3d DCA 1966) (“In contract actions, the complaint must allege the execution of the contract, the obligation thereby assumed, and the breach.”).…
  • Brooks Tropicals, Inc. v. Alcides Acosta, 959 So. 2d 288 (Fla. 3d DCA 2007)
    …as D. Lardin, P.A., 938 So. 2d 571, 575 (Fla. 4th DCA 2006) (confirming that the “elements of a breach of contract action are: (1) a valid contract; (2) a material breach; and (3) damages”) (citation omitted); J.J. Gumberg Co. v. Janis Servs., Inc., 847 So. 2d 1048, 1049 (Fla. 4th DCA 2003). We also find nothing in the promise identified in Acosta’s trial testimony to preclude a claim for the packing house’s losses stemming from lost fruit production. See Merin Hunter Codman, Inc. v. Wackenhut Corrections Cor…
  • …(citing Loewer v. N.Y. Life Ins. Co., 773 F.Supp. 1518, 1521 (M.D.Fla.1991)). The elements for bringing a cause of action for breach of contract are: (1) a valid contract; (2) material breach; and (3) damages. J.J. Gumberg Co. v. Janis Servs., Inc., 847 So. 2d 1048, 1049 (Fla. 4th DCA 2003). The real issue in this case is when did plaintiffs cause of action accrue? In this case, the last element giving rise to the cause of action was the damages that arose from the grounding of the plane. Had the airplane nev…

Previewing 3 of 21 citing cases — full citator treatment, depth of discussion, and citing context are member features.

Join FLexlaw to unlock all legal intelligence

Authorities Cited

Full citator, related cases, and AI research tools

Open in FLexlaw