IN RE MIAMI RAILROAD STATION

Fla. Railroad & P. U. C. | 1962-05-17
Nos. 3; No. 1696
Chairman WILBUR C. KING, Commissioners JERRY W. CARTER and EDWIN L. MASON participated in the disposition of this matter.
19 Fla. Supp. 133 Florida Railroad & Public Utilities Commission (1962)

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

The Florida Railroad & Public Utilities Commission ordered the Florida East Coast Railway Company to file a detailed progress report on its compliance with a 1955 order to construct a new passenger station in Miami, after finding the company had adequate time since its reorganization to make substantial progress on the project.


Holding

The Commission directed the Florida East Coast Railway Company to file a comprehensive progress report by May 25, 1962, addressing six specific questions regarding the status of yard clearance, completion of architectural plans, contract execution, expected construction commencement and completion dates, and the timeline for removing the existing downtown passenger station.


Key Quotes

“the new and present owners of said Florida East Coast Railway Company have had possession of said railroad properties for more than one year”

Establishes that the company had sufficient time to make progress on the construction obligation.

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

In 1955, the Commission ordered the trustees of the Florida East Coast Railway to construct a new passenger station in Miami at Buena Vista Yards. Thi…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.

Opinion of the Court
BY THE COMMISSION.

BY THE COMMISSION.

Whereas, in 1955 this commission entered its order requiring the trustees of the Florida East Coast Railway to construct a new passenger station in the city of Miami at its Buena Vista Yards; and

Whereas, said order has been approved by the Interstate Commerce Commission, the United States District Court, and the new owners of the Florida East Coast Railway Company; and

Whereas, the construction of said new passenger station, as required by order of this commission, has been made a part of the plan of reorganization of said Florida East Coast Railway, and is now an obligation of said railway company; and

____Whereas, the new and present owners of said Florida East Coast Railway Company have had possession of said railroad properties for more than one year; and

Whereas, it appears to this commission that the said Florida East Coast Railway Company, since reorganization, has had ample time to make substantial progress in complying with this commission’s order to construct a new passenger station in the city of Miami.

Now, therefore, in consideration thereof, it is ordered that the Florida East Coast Railway Company he and it is hereby directed to file with this commission on, or before, Friday, May *13425, 1962, a full and complete report on the progress it has made in the construction of said new passenger station. Said report, among other things, shall answer the following specific questions, if possible—

1. What progress has been made in clearing the Buena Vista Yards to make way for the construction thereon of said new passenger station?

2. Have architect’s plans for said new passenger station been completed, and if not, when will they be completed and a copy furnished to this commission?

3. Has a contract been entered into for the construction of said new passenger station, and, if not, when will said contract be executed?

4. What date does the railway company expect to begin actual construction of said new passenger station?

5. What date does the railway company expect to complete the construction of said new passenger station?

6. When does the railway company expect to complete the physical removal of the present passenger station in downtown Miami?