CHRISTOPHER J. UNNERSTALL AND LYNETTE M. UNNERSTALL, PETITIONERS,
v.
DESIGNERICK, INC., A FLORIDA CORPORATION, RESPONDENT
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
The court held that the lienor's counterclaims for money damages did not satisfy the statutory requirement to show cause why the lien should not be discharged.
[1] Mandamus is the appropriate procedural vehicle to compel a trial court to discharge a construction lien.
[2] A lienor must strictly comply with the requirements of section 713.21(4), Florida Statutes, to avoid cancellation of its lien after a property owner invokes the statute.
Previewing 2 of 4 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.
Join FLexlaw to unlock all legal intelligenceThe Unnerstalls sought to discharge Designerick's construction lien. Designerick responded with counterclaims for breach of contract, open account, an…
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Open Account cases and more on FLexlaw
Christopher and Lynette Unnerstall seek review of an order that denies their motion to discharge Designerick, Inc.’s construction lien on their property. They argue that Designerick’s answer and counterclaims failed to strictly comply with the requirements of section 713.21(4), Florida Statutes (2008),1 to avoid cancellation of the lien. Although the Unnerstalls filed a petition for a writ of certiorari in this court seeking to have the lien discharged, we treat the petition as one for mandamus and grant the petition. See Brookshire v. GP Constr. of Palm Beach, Inc., 993 So.2d 179 (Fla. 4th DCA 2008) (holding that mandamus is the appropriate vehicle to compel the trial court to discharge a lien).
Designerick recorded a claim of lien against the Unnerstalls’ property because the Unnerstalls failed to pay the balance of $21,985 due for the installation of cabinets. The Unnerstalls filed a complaint to cancel the lien and for an order to show cause. Designerick responded with an answer to the complaint asserting affirmative defenses and counterclaims alleging breach of oral contract, open account, and unjust enrichment. When the Unnerstalls moved to discharge the lien, Designerick served its opposition to the motion to discharge the lien, stating that it had properly filed its counterclaims within the twenty days, as required by section 713.21(4). The trial court denied the motion to discharge the lien on the ground that Desig-*902nerick’s counterclaims satisfied the requirements of the statute.
The language of the lien discharge statute requires that an action for lien enforcement be filed within twenty days or that cause be shown within that period why enforcement should not be commenced. § 713.21(4); Matrix Constr. Corp. v. Mecca Constr., Inc., 578 So.2d 388, 389 (Fla. 3d DCA 1991) (noting that “one whose property has been liened is granted the right to initiate a petition creating a twenty-day limit in which to assert by counterclaim or otherwise a foreclosure of the lien under section 713.21(4)”). When a property owner invokes the statute, a lien- or must strictly comply with the statute in order to preserve its lien. Ruffolo v. Parish & Bowman, Inc., 966 So.2d 434 (Fla. 1st DCA 2007).
Designerick argues that its counterclaims were sufficient to avoid discharge, citing Mainlands Construction Co. v. Wen-Dic Construction Co., 482 So.2d 1369 (Fla.1986), in support of its argument. Mainlands is distinguishable from this case because the lienor in Mainlands sought foreclosure of the mechanic’s lien in its counterclaim. Id. In contrast, Desig-nerick did not request foreclosure, but instead alleged breach of contract and other causes of action seeking money damages. The assertion of these causes of action did not preserve its right to pursue foreclosure of the lien. See Brookshire, 993 So.2d at 180 (holding that the lienor’s motion to arbitrate filed in response to a complaint to discharge the lien did not meet the requirement of the statute that an action to enforce the lien be commenced within twenty days); Dracon Constr., Inc. v. Facility Constr. Mgmt., Inc., 828 So.2d 1069, 1071 (Fla. 4th DCA 2002) (holding that the lienor’s barebones answer did not comply with the statutory requirement that an action to enforce the lien be filed or cause be shown why no action need be commenced within the twenty-day period). Consequently, we grant the petition and direct the trial court to discharge the lien.2
Petition granted.
WHATLEY, J., and DAKAN, STEPHEN L., Associate Senior Judge, Concur.
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By
-
Hernandez v. Burleigh House Condo., Inc., 419 So. 3d 169 (Fla. 3d DCA 2025)
-
Stein v. Reynolds Ventures, Inc. (Fla. 2d DCA 2026)
Authorities Cited
- Mainlands Constr. Co., Inc. v. Wen-Dic Constr. Co., Inc., 482 So. 2d 1369 (Fla. 1986)
- Dracon Constr., Inc. v. Facility Constr. Mgmt., Inc., 828 So. 2d 1069 (Fla. 4th DCA 2002)
- Matrix Constr. Corp. v. Mecca Constr., Inc., 578 So. 2d 388 (Fla. 3d DCA 1991)
- Brookshire v. GP Constr. OF Palm Beach, Inc., 993 So. 2d 179 (Fla. 4th DCA 2008)
- Ruffolo v. Parish & Bowman, Inc., 966 So. 2d 434 (Fla. 1st DCA 2007)