HUMBERTO MARIN, APPELLANT,
v.
AARON'S RENT TO OWN AND BROADSPIRE, APPELLEES

Fla. 1st DCA | 2010-12-03
No. 1D10-0824
LEWIS and CLARK, JJ., concur., KAHN, J., Concurs with Opinion.
53 So. 3d 1048 Florida District Court of Appeal, First District (2010) Negative Treatment
Cited by 12 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

In this workers' compensation appeal, the court affirmed the denial of permanent total disability benefits but modified the award of a physiatrist in Colombia by striking the condition precedent that the claimant obtain a referral from his authorized treating orthopedist, finding that the employer-carrier was bound by its pretrial stipulation to provide a physiatrist without conditions.


Holding

The court held that the employer-carrier was bound by its pretrial stipulation to provide a physiatrist in Colombia without additional conditions. The court reversed the JCC's modification requiring a referral and struck the errant findings and conclusions adding this condition.


Headnotes

[1] A pretrial stipulation is binding on the parties and the court unless there are grounds for avoidance or modification, such as fraud, misrepresentation, or concealment.

[2] A party cannot avoid a binding stipulation based solely on a change in litigation strategy.

Previewing 2 of 5 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Key Quotes

“a stipulation properly entered into and relating to a matter upon which it is appropriate to stipulate is binding upon the parties and upon the Court”

Establishes the fundamental principle that pretrial stipulations are binding absent specific grounds for voiding them

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Claimant suffered a compensable right knee injury on June 4, 1998. After reaching age 62, he retired and moved to Colombia in June 2004. The parties e…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
PER CURIAM.

PER CURIAM.

In this workers’ compensation appeal, Claimant challenges an order of the Judge of Compensation Claims (JCC) that denies permanent total disability (PTD) benefits and awards the authorization of a physia-trist in Colombia, though with a condition precedent — which Claimant contends is in variance with the terms of the parties’ stipulation. We affirm the JCC’s denial of PTD without further comment, and write to address the award of a physiatrist in Colombia. Based on our analysis, we modify the award of a physiatrist by striking errant findings and conclusions, and affirm the order as modified.

Claimant suffered a compensable right knee injury on June 4, 1998, for which he was provided authorized medical care in the United States. After reaching the age of sixty-two, Claimant retired from his employment and moved to his native country of Colombia, in June of 2004. Claimant then filed a petition for benefits (PFB) for authorization of a physiatrist in Colombia. On April 4, 2008, the parties entered into a pretrial statement wherein the E/C stipulated that it would furnish Claimant a phy-siatrist in Colombia, without conditions or contingencies.

A final hearing was held on September 22, 2009, nearly 18 months after the parties entered into the stipulation. For the first time, the E/C sought to amend the pretrial stipulation to add the defense of medical necessity in response to the claim for authorization of a physiatrist. In the merit order which followed, the JCC concluded the E/C was bound by its April 8, 2008 stipulation to provide a physiatrist in Colombia. Nevertheless, the JCC ordered that the E/C provide a physiatrist in Colombia “upon referral” from Claimant’s authorized treating orthopedist (also in Colombia), thus modifying and rewriting the agreement which Claimant sought to enforce. Claimant brought this irregularity to the JCC’s attention via a motion for rehearing and the motion was denied without comment.

On appeal, Claimant contends that absent sufficient grounds for avoidance or modification, both the JCC and the E/C were bound by the E/C’s April 8, 2008 stipulation to provide a physiatrist in Colombia — with no additional conditions.

The primary purpose of a pretrial stipulation is to provide the parties an opportunity to state and simplify the issues to be determined by the JCC. See Fla. Admin. Code R. 60Q-6.113(2)(a)-(f). To effectuate this purpose, parties are encouraged to enter into stipulations to limit the issues for consideration and eliminate unnecessary proof. Id. Because due process rights are implicated, a party has a right to rely upon the issues as framed in the pretrial statement. See Isaac v. Green Iguana, Inc., 871 So.2d 1004 (Fla. 1st DCA 2004) (reversing denial of compensation based on affirmative defense not raised pretrial). Although the rules of workers’ compensation procedure allow a party to amend its pretrial statement whenever such amendment is approved by the JCC, (See Fla. Admin. Code R. 60Q-6.113(4)), this administrative rule does not alter substantive law governing the binding nature of stipulations and agreements. See generally Turner v. Miami-Dade County Sch. Bd., 941 So.2d 508, 509 (Fla. 1st DCA 2006) (“As a general rule, a stipulation properly entered into and relating to a *1050matter upon which it is appropriate to stipulate is binding upon the parties and upon the Court.” (internal citations and quotation marks omitted)); Jacobs v. Volker Stevin Constr., 609 So.2d 132, 133 (Fla. 1st DCA 1992) (JCC may void or modify a stipulation founded on fraud, misrepresentation, or concealment); Gus Stephens Drywall v. Durr, 569 So.2d 844, 845 (Fla. 1st DCA 1990) (A stipulation should not be ignored absent showing of fraud, overreaching, or misrepresentation).

Although the regular course of litigation commonly requires parties to amend or supplement claims, defenses, objections, or witnesses, as provided for in Rule 60Q-6.113(4), the circumstances presented here do not present a mere amendment or supplement to a defense. Here, in response to Claimant’s PFB for authorization of a physiatrist in Colombia, the E/C not only failed to raise the medical necessity defense in the pretrial statement, but took the additional and affirmative step of entering into a stipulation to provide a physiatrist in Colombia, obviating any defense or requirement of further proof. The JCC approved and found the stipulation binding and enforceable. Notwithstanding the friendlier title bestowed by the E/C, its purported amendment under the facts presented here was, in substance, an attempt to void or set aside a binding stipulation previously approved by the JCC. While there are certainly occasions which might require the voiding of a stipulation or agreement, a party’s mere change of litigation strategy, without more, provides insufficient grounds to set aside a binding agreement. See Lockheed Space Operations v. Pham, 600 So.2d 1261, 1263 (Fla. 1st DCA 1992) (party cannot avoid binding stipulation because he “falls out of love” with his earlier litigation strategy). Accordingly, here the JCC erred in modifying the terms of the parties’ agreement in the absence of any asserted or ostensible legal basis for such relief. Cf. Salinas v. C.A.T. Concrete, LLC, 46 So.3d 600 (Fla. 1st DCA 2010) (explaining legal bases for voiding stipulations).

It is never a court’s function to rewrite the terms of an agreement to make it more reasonable. See Churchville v. GACS Inc., 973 So.2d 1212, 1216 (Fla. 1st DCA 2008). The JCC effectively rewrote the terms of the stipulation to require that the E/C would provide a physia-trist in Columbia “upon referral” from Claimant’s authorized treating orthopedist. The joint stipulation of the parties is binding on the JCC, and a finding by the JCC at variance with the stipulation will be overturned. Wright v. Golf Drive Residence, Inc., 412 So.2d 884 (Fla. 1st DCA 1982). Here, the parties’ joint agreement simply provides that the E/C “will provide” a physiatrist in the area of Claimant’s residence (Colombia). Neither party asserts any ambiguity in this agreement. Accordingly, the order on appeal is hereby modified by striking any requirement that Claimant obtain a referral before receiving authorization for a physiatrist. See Lawrence v. Aquarius Sales & Serv., Inc., 30 So.3d 690 (Fla. 1st DCA 2010) (modifying order by striking JCC’s errant findings, and affirming as modified).

Except as modified, the order is AFFIRMED.

LEWIS and CLARK, JJ., concur.

KAHN, J., Concurs with Opinion.

KAHN, J.,

concurring.

I agree with the majority opinion. In fact, that opinion is a fine and concise explanation of the use of stipulations by parties to workers’ compensation matters. Unfortunately, the opinion is in conflict with Salinas v. C.A.T. Concrete, LLC, 46 So.3d 600 (Fla. 1st DCA 2010). In Sail- *1051 nas, a panel of this court held, “a JCC is not required to follow a stipulation that is refuted by competent, substantial evidence.” Id. at 600.

Here, given the length of time between the stipulation and the hearing, the E/C argued that medical necessity no longer supported provision of the medical specialty in question. The JCC quite correctly nixed such an objection; but, under Salinas, it appears such an objection could be made. Interestingly, counsel for appellee, the same able lawyer who represented the successful party in Salinas, characterizes Salinas as a case involving “a stipulation rejected as against public policy....” (Answer Brief, p. 28, n. 7) Salinas does not really articulate such a rationale, but instead relies upon evidence purportedly countermanding the parties’ stipulation in that case. More specifically, the case law relied upon in Salinas is Fast Tract Framing, Inc. v. Caraballo, 994 So.2d 355 (Fla. 1st DCA 2008), a case simply construing a statute. That statute, section 440.02(28), Florida Statutes (2007), an enactment the majority in Caraballo characterized as unambiguous, mandates that wages, for purposes of the Florida Workers’ Compensation Act, and therefore for the purpose of calculating average weekly wage, include only those wages “earned and reported for federal income tax purposes.... ” See id. at 356.

In the present case, and by correct analogy to the situation in Salinas, long-standing statutory law mandates “the employer shall furnish to the employee such medically necessary remedial treatment, care, and attendance for such period as the nature of the injury or the process of recovery may require .... ” § 440.13(2)(a), Fla. Stat. (2009). By the stipulation here at issue, the E/C agreed that the claimant would be relieved of her burden to demonstrate medical necessity under the statute, just as the employer in Salinas had stipulated that Mr. Salinas would be relieved of his burden of demonstrating average weekly wage, thus “removing certain elements of the claim from consideration by the JCC.” See Salinas, 46 So.3d at 603 (Kahn, J. dissenting.). Despite that stipulation, the E/C argued to the JCC, successfully it seems, that medical necessity would still be an issue in the provision of care. Today’s opinion holds that the E/C was bound by its stipulation despite the apparent existence of evidence raising a question concerning present medical necessity; contrariwise, the E/C in Salinas prevailed on appeal in a situation where, just as here, the JCC allowed presentation of evidence that impeached the stipulation. I have a great deal of difficulty in drawing a significant procedural distinction between this case and Salinas.

With these observations, I concur.

Concurrence
KAHN, J.,

KAHN, J.,

concurring.

I agree with the majority opinion. In fact, that opinion is a fine and concise explanation of the use of stipulations by parties to workers’ compensation matters. Unfortunately, the opinion is in conflict with Salinas v. C.A.T. Concrete, LLC, 46 So. 3d 600 (Fla. 1st DCA 2010). In Sail- nas, a panel of this court held, “a JCC is not required to follow a stipulation that is refuted by competent, substantial evidence.” Id. at 600.

Here, given the length of time between the stipulation and the hearing, the E/C argued that medical necessity no longer supported provision of the medical specialty in question. The JCC quite correctly nixed such an objection; but, under Salinas, it appears such an objection could be made. Interestingly, counsel for appellee, the same able lawyer who represented the successful party in Salinas, characterizes Salinas as a case involving “a stipulation rejected as against public policy....” (Answer Brief, p. 28, n. 7) Salinas does not really articulate such a rationale, but instead relies upon evidence purportedly countermanding the parties’ stipulation in that case. More specifically, the case law relied upon in Salinas is Fast Tract Framing, Inc. v. Caraballo, 994 So. 2d 355 (Fla. 1st DCA 2008), a case simply construing a statute. That statute, section 440.02(28), Florida Statutes (2007), an enactment the majority in Caraballo characterized as unambiguous, mandates that wages, for purposes of the Florida Workers’ Compensation Act, and therefore for the purpose of calculating average weekly wage, include only those wages “earned and reported for federal income tax purposes.... ” See id. at 356.

In the present case, and by correct analogy to the situation in Salinas, long-standing statutory law mandates “the employer shall furnish to the employee such medically necessary remedial treatment, care, and attendance for such period as the nature of the injury or the process of recovery may require .... ” § 440.13(2)(a), Fla. Stat. (2009). By the stipulation here at issue, the E/C agreed that the claimant would be relieved of her burden to demonstrate medical necessity under the statute, just as the employer in Salinas had stipulated that Mr. Salinas would be relieved of his burden of demonstrating average weekly wage, thus “removing certain elements of the claim from consideration by the JCC.” See Salinas, 46 So. 3d at 603 (Kahn, J. dissenting.). Despite that stipulation, the E/C argued to the JCC, successfully it seems, that medical necessity would still be an issue in the provision of care. Today’s opinion holds that the E/C was bound by its stipulation despite the apparent existence of evidence raising a question concerning present medical necessity; contrariwise, the E/C in Salinas prevailed on appeal in a situation where, just as here, the JCC allowed presentation of evidence that impeached the stipulation. I have a great deal of difficulty in drawing a significant procedural distinction between this case and Salinas.

With these observations, I concur.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • Knight v. Walgreens and Sedgwick CMS, 109 So. 3d 1224 (Fla. 1st DCA 2013)
    …a neurosurgeon, except to the extent that this claim was precluded by Claimant’s alleged misrepresentations. Given that the purpose of the pretrial stipulation is to put the parties on notice of what is in dispute, see Marin v. Aaron’s Rent To Own, 53 So. 3d 1048 (Fla. 1st DCA 2010) (holding primary purpose of pretrial stipulation in workers’ compensation is to provide parties an opportunity to state and simplify issues to be determined by the JCC), and considering that Claimant could have obtained other med…
  • Leon v. CSB Servs., Inc., 219 So. 3d 166 (Fla. 1st DCA 2017)
    …ust Brakes, 75 So. 3d 807 (Fla. 1st DCA 2011). Moreover, in the specific factual circumstances presented by this case, the E/C waived a challenge to medical necessity by not asserting it in the pretrial stipulation. Cf. Marin v. Aaron’s Rent To Own, 53 So. 3d 1048, 1050 (Fla. 1st DCA 2010) (“Here, in response to Claimant’s PFB for authorization of a physiatrist -in Colombia, the E/C not only failed to raise the medical necessity defense in the pretrial statement, but took the additional and affirmative step o…
  • S & M Transp., Inc. v. Northland Ins. Co., 208 So. 3d 230 (Fla. 5th DCA 2016)
    …presented at trial and decided by the jury. “[T]he purpose of the pretrial stipulation is to put the parties on notice of what is in dispute .... ” Knight v. Walgreens, 109 So. 3d 1224, 1228 (Fla. 1st DCA 2013) (citing Marin v. Aaron’s Rent To Own, 53 So. 3d 1048 (Fla. 1st DCA 2010)). Although the parties could have also agreed to have the jury determine damages, they did not do so, and by their pretrial stipulation, they limited the only issue for the jury to determine was whether there was a theft of S & M…

Previewing 3 of 7 citing cases — full citator treatment, depth of discussion, and citing context are member features.

Join FLexlaw to unlock all legal intelligence

Authorities Cited (11 total)

View all 11 cited authorities →

Full citator, related cases, and AI research tools

Open in FLexlaw