ROYAL PALMS SENIOR APARTMENTS LIMITED PARTNERSHIP
v.
CONSTRUCTION ENTERPRISES, INC. OF TENNESSEE D/B/A CONSTRUCTION ENTERPRISES, INC. FORUM ARCHITECTURE & INTERIOR DESIGN INC., BH-FFS, LLC D/B/A BRADCORP FLORIDA II, LLC, ET AL.

Fla. 5th DCA | 2019-04-12
No. 18-2182
Cohen, J., Berger, J., Edwards, J., Mahl, J.
Florida District Court of Appeal, Fifth District (2019)

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.


Holding

A valid arbitration agreement existed in the parties' construction contract, but the trial court must determine on remand whether Royal Palms' claim arose before or after final payment was due, as only claims arising before final payment are subject to mandatory arbitration under the contract.


Headnotes

[1] A valid arbitration agreement exists when a construction contract's general conditions and supplementary conditions, read together, establish an exclusive dispute resolut…

[2] While ambiguities regarding the scope of an arbitration clause should be resolved in favor of arbitration, the existence of an enforceable arbitration clause itself shoul…

Previewing 2 of 5 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Key Quotes

“Under both federal statutory provisions and Florida's arbitration code, there are three elements for courts to consider in ruling on a motion to compel arbitration of a given dispute: (1) whether a valid written agreement to arbitrate exists; (2) whether an arbitrable issue exists; and (3) whether the right to arbitration was waived.”

This establishes the three-part test courts must apply when determining whether to enforce an arbitration agreement.

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

In December 2006, Royal Palms and CEI entered into a construction contract comprised of AIA General Conditions and Supplementary Conditions that modif…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
Edwards

IN THE DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA

FIFTH DISTRICT

NOT FINAL UNTIL TIME EXPIRES TO

FILE MOTION FOR REHEARING AND

DISPOSITION THEREOF IF FILED

ROYAL PALMS SENIOR APARTMENTS

LIMITED PARTNERSHIP,

Appellant,

v. Case No. 5D18-2182

CONSTRUCTION ENTERPRISES, INC.

OF TENNESSEE D/B/A CONSTRUCTION

ENTERPRISES, INC. FORUM ARCHITECTURE

& INTERIOR DESIGN INC., BH-FFS, LLC D/B/A BRADCORP FLORIDA II, LLC, ET AL.,

Appellees.

________________________________/

Opinion filed April 12, 2019

Nonfinal Appeal from the Circuit Court for Brevard County, Jeffrey Mahl, Judge.

James. C. Prichard, Evan J. Small, Megan

A. Picataggio, and Greg K. Demers, of Ball

Janik LLP, Orlando, for Appellant.

Jeffrey M. Paskert and Dara L. Dawson, of Mills Paskert Divers P.A., Tampa, for Appellee, Construction Enterprises Inc. of Tennessee d/b/a Construction Enterprises, Inc.

No Appearance for Other Appellees.

COHEN, J.

1 Royal Palms also argues that the trial court applied an improper standard in determining that a valid arbitration agreement existed. The trial court never announced what standard it used in making its determination, and thus, this argument lacks merit.

AFFIRMED, in part, REVERSED, in part; and REMANDED.

BERGER and EDWARDS, JJ., concur.

Footnotes
2 Royal Palms Senior Apartments Limited Partnership (“Royal Palms”) appeals the nonfinal order entered in favor of Construction Enterprises Inc. of Tennessee d/b/a Construction Enterprises, Inc. (“CEI”) staying Royal Palms’ lawsuit pending mediation and arbitration. Royal Palms argues that the trial court erred in finding that a valid arbitration agreement existed and that its claim was subject to arbitration.1 We affirm the trial court’s finding that the parties had a valid agreement to arbitrate certain claims. However, because it is unclear whether Royal Palms’ claim was one subject to arbitration, we remand for a determination of that issue. In December 2006, the parties entered into a contract for CEI to construct the Royal Palms Senior Apartments. The agreement was comprised of the “AIA Document A201–1997 General Conditions of the Contract for Construction” (“General Conditions”) and a supplementary document (“Supplementary Conditions”), which modified and deleted portions of the General Conditions and controlled if the two documents conflicted. In October 2017, Royal Palms filed a complaint against CEI alleging negligence, vicarious liability, breach of contract, and breach of applicable building codes. CEI moved to dismiss or alternatively, to compel mandatory and exclusive dispute resolution procedures, including mediation and arbitration. After a hearing on CEI’s motion, the trial court determined that the mediation and arbitration provisions of the General Conditions were binding and enforceable. It stayed the case and ordered mediation followed by arbitration if mediation was unsuccessful. This appeal followed.
3 “Under both federal statutory provisions and Florida’s arbitration code, there are three elements for courts to consider in ruling on a motion to compel arbitration of a given dispute: (1) whether a valid written agreement to arbitrate exists; (2) whether an arbitrable issue exists; and (3) whether the right to arbitration was waived.” Seifert v. U.S. Home Corp., 750 So. 2d 633, 636 (Fla. 1999) (quoting Terminix Int’l Co. v. Ponzio, 693 So. 2d 104, 106 (Fla. 5th DCA 1997)). Here, Royal Palms’ arguments implicate only the first two prongs of the Seifert test. Although courts generally favor arbitration, “no party may be forced to submit a dispute to arbitration that the party did not intend and agree to arbitrate.” Id. (citing Seaboard Coast Line R.R. v. Trailer Train Co., 690 F. 2d 1343, 1352 (Fla. 1982)). Thus, while ambiguities regarding prong two—the scope of an arbitration clause—should be resolved in favor of arbitration, prong one—the existence of an enforceable arbitration clause—should not. See Seaboard, 690 F. 2d at 1352 (“Although Federal policy requires us to resolve any doubt about the application of an arbitration clause in favor of arbitration, the Federal policy cannot serve to stretch a contract beyond the scope originally intended by the parties.” (citations omitted)). While the Supplemental Conditions eliminated some of the General Conditions related to arbitration, multiple provisions contemplating arbitration remained. “An interpretation of a contract which gives a reasonable, lawful and effective meaning to all of the terms is preferred to an interpretation which leaves a part unreasonable, unlawful or of no effect.” Nabbie v. Orlando Outlet Owner, LLC, 237 So. 3d 463, 466 (Fla. 5th DCA 2018) (citing Seabreeze Rest., Inc. v. Paumgardhen, 639 So. 2d 69, 71 (Fla. 2d DCA 1994)).
4 Pursuant to the General Conditions as modified by the Supplementary Conditions, the “exclusive procedure[]” for resolving claims arising before final payment is due is to submit such claims to the Architect for a final, binding decision. If the parties are not satisfied with the Architect’s decision, they may mediate the claim. If mediation is unsuccessful, the only remaining option is to arbitrate the claim. Thus, because the General Conditions as modified by the Supplementary Conditions require arbitration of claims arising before final payment is due if the parties are unsatisfied with the Architect’s decision and mediation is unsuccessful, we find that the trial court did not err in determining that the parties had a valid agreement to arbitrate. However, the contract is silent regarding the procedure for resolving claims that arise after final payment is due. The provisions comprising the “exclusive procedures” for resolving such claims reference litigation, mediation, and arbitration. Because those claims are not required to be submitted to the Architect, they are not subject to arbitration if mediation is unsuccessful. A party cannot be forced to arbitrate a claim it did not agree to arbitrate. See Seifert, 750 So. 2d at 633 (citing Seaboard, 690 F. 2d at 1352). The record is less clear regarding the second prong of the Seifert test—whether Royal Palms’ claim was an arbitrable issue. The trial court’s order mandating mediation followed by arbitration did not include a determination of whether Royal Palms’ claim arose before or after final payment was due. Thus, it is unclear whether Royal Palms was required to arbitrate its claim. Accordingly, we remand for a determination of that matter and proceedings, if any, consistent with this opinion.

Cases With Similar Vibessemantic neighbors from the corpus


Citator

Authorities Cited

Full citator, related cases, and AI research tools

Open in FLexlaw