MAURO LEDER AND PATRICIA LEDER
v.
IMBURGIA CONSTRUCTION SERVICES, INC.
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
The Owners sued the Contractor for breach of a construction contract, but the Contractor moved to dismiss based on an arbitration clause. The trial court granted the motion to dismiss, finding the Owners failed to comply with dispute resolution provisions. The appellate court reversed, holding that the Contractor waived its right to arbitration by failing to initiate the contractually required prerequisite steps before arbitration.
The court reversed the trial court's dismissal and held that the Contractor waived its right to arbitration based on its pre-litigation inaction and the contract's clear requirement that parties submit claims to the Initial Decision Maker before pursuing arbitration. Because neither party followed the contractually mandated prerequisite steps, the right to arbitration was waived, and the case must proceed in court rather than arbitration.
[1] A party may waive its right to arbitration by failing to comply with mandatory contractual conditions precedent to arbitration, such as submitting a claim to a designated…
[2] Waiver of an arbitration agreement is analyzed under a totality-of-circumstances test to determine whether the party acted inconsistently with its arbitration right, and…
Previewing 2 of 5 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.
Join FLexlaw to unlock all legal intelligence“The question of whether there has been waiver in the arbitration agreement context should be analyzed in much the same way as in any other contractual context. The essential question is whether, under the totality of the circumstances, the defaulting party has acted inconsistently with the arbitration right.”
This establishes the legal standard for determining whether a party has waived its right to arbitration.
Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.
Join FLexlaw to unlock all legal intelligenceThe Owners and Contractor executed a written construction contract containing a binding dispute resolution clause requiring submission to an Initial D…
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Condition Precedent To Arbitration cases and more on FLexlaw
HENDON, J.
The plaintiffs below, Mauro Leder and Patricia Leder (collectively, “Owners”), appeal from a county court order granting Imburgia Construction Services, Inc.’s (“Contractor”) motion to dismiss the Owners’ amended complaint. For the reasons that follow, we reverse the order under review and remand with directions.
The Owners and the Contractor entered into a written construction contract for renovations to the Owners’ home. The contract executed by the parties provides for arbitration as the method for binding dispute resolution. However, prior to arbitration, the parties are required to submit any claim, which includes disputes related to the contract, to the Initial Decision Maker, who the parties agreed would be the Miami Shores Village Building Department Official. A claim must be initiated within twenty-one days of the occurrence of the event giving rise to the claim. Pending resolution of a claim, the Contractor is required to proceed diligently with the performance of the contract, and the Owners are required to make payments in accordance with the contract. The initial decision by the Initial Decision Maker is a condition precedent to mediation, and mediation is a condition precedent to arbitration. The parties’ contract reflects that the parties’ right to proceed to binding dispute resolution—arbitration—is waived if a certain condition precedent to arbitration is not followed.
In January 2020, the Owners initiated an action against the Contractor, and thereafter, filed an amended complaint, seeking monetary damages. In the amended complaint, the Owners asserted that on June 25, 2019, the Contractor presented a fifth change order for structural work, which the Owners refused to execute, questioning both the necessity and the price. The Owners alleged that the Contractor then abandoned the job and failed to file a claim with the Initial Decision Maker, thereby waiving any right to proceed under the contract’s dispute resolution procedures. The Owners further alleged that the Contractor left unpaid subcontractor bills, and the amounts paid by the Owners exceeded the value of the work performed by the Contractor. The Contractor moved to dismiss the amended complaint, without specifically seeking to compel arbitration. The Contractor argued that the contract stipulates for arbitration, but the Owners filed the lawsuit in contravention of the contract, thereby failing to adhere to the dispute resolution provisions. Despite not specifically seeking arbitration, the Contractor cited to section 682.181(1) of the Florida Statutes, which provides that “[a] court of this state having jurisdiction over the controversy and the parties may enforce an agreement to arbitrate.” Further, the Contractor set forth the factors a court is to consider when ruling on a motion to compel arbitration—(1) whether a valid agreement to arbitrate exists; (2) whether an arbitrable issue exists; and (3) whether the right to arbitration was waived, and asserted that “there is a valid written agreement with arbitrable issues and the Defendant has not waived its right to arbitrate.”
Following a hearing, the trial court granted the Contractor’s motion to dismiss the amended complaint. In its order, the trial court stated as follows:
THIS COURT finds that the parties entered into a contract with a valid Binding Dispute Resolution Clause, wherein both parties agreed and elected to resolve disputes through Arbitration. Plaintiff failed to comply with any of the Dispute Resolution provisions. The Court further finds that Plaintiff’s claim arises out of the parties’ agreement and therefore Plaintiff’s Amended Complaint is improper, and its argument of waiver has no merit since Defendant has not asserted any claims for damages.
The trial court’s dismissal of the amended complaint left the Owners without a remedy for the Contractor’s alleged wrongdoings. The Owners’ timely appeal followed.
“[W]hether a party has waived the right to arbitrate is a question of fact, reviewed on appeal for competent, substantial evidence to support the lower’s court’s findings.” Green Tree Servicing, LLC v. McLeod, 15 So. 3d 682, 686 (Fla. 2d DCA 2009). However, “the standard of review applicable to the trial court’s construction of the arbitration provision, and to its application of the law to the facts found, is de novo.” Id. at 686-87.
The Owners contend that the arbitration provision in the contract is unenforceable as it was waived. We agree.
Although a dispute arose between the parties, neither party initiated a claim with the Initial Decision Maker. Under the contract, a condition precedent to mediation is filing a claim with the Initial Decision Maker, and a condition precedent to arbitration is demanding mediation of the Initial Decision Maker’s decision. In this case, either party had the ability to initiate a claim with the Initial Decision Maker because the dispute relating to the fifth change order affected both parties and was related to the construction contract. However, neither party elected to do so.
As recognized by the Contractor in its motion to dismiss the amended complaint, “[i]n determining whether a dispute is subject to arbitration, courts consider at least three issues: (1) whether a valid written agreement to arbitrate exists: (2) whether an arbitrable issue exists; and (3) whether the right to arbitration was waived.” Green Tree, 15 So. 3d at 686 (quoting Stacy David, Inc. v. Consuegra, 845 So. 2d 303, 306 (Fla. 2d DCA 2003)).
In the instant case, there is no dispute that there was a valid written agreement to arbitrate and that there was an arbitrable issue. The parties, however, disagree as to whether the Contractor waived its contractual right to arbitrate.
“[T]he question of whether there has been waiver in the arbitration agreement context should be analyzed in much the same way as in any other contractual context. The essential question is whether, under the totality of the circumstances, the defaulting party has acted inconsistently with the arbitration right.” Green Tree, 15 So. 3d at 687 (quoting Nat’l Found. for Cancer Rsch. v. A.G. Edwards & Sons, Inc., 821 F. 2d 772, 774 (D.C. Cir. 1987)). Waiver of an arbitration clause “may be predicated on both pre-and post-suit actions in tandem.” Bland v. Green Acres Grp., L.L.C., 12 So. 3d 822 (Fla. 4th DCA 2009). The “prosecution or defense of a lawsuit on issues subject to arbitration may constitute a waiver.” Green Tree, 15 So. 3d at 687 (quoting Seville Condo. #1, Inc. v. Clearwater Dev. Corp., 340 So. 2d 1243, 1245 (Fla. 2d DCA 1976)). Moreover, “a party may waive his or her right to arbitration by filing a lawsuit without seeking arbitration; by filing an answer to a pleading seeking relief without raising the right to arbitration; and by moving for summary judgment.” Green Tree, 15 So. 3d at 687 (internal citations omitted).
In the instant case, the Contractor waived its right to arbitrate based on its pre-litigation action and the language in the parties’ contract. As stated above, prior to binding arbitration, there are other steps that the parties to the contract must take to preserve its contractual right to arbitrate—submitting a claim to the Initial Decision Maker, and thereafter, pursuing mediation. Neither party utilized this procedure to resolve their dispute relating to the fifth change order, including taking the first step— initiating a claim with the Initial Decision Maker. As such, we conclude that the parties waived their right to arbitrate under the terms of their contract.
Therefore, we reverse the order granting the Contractor’s motion to dismiss the amended complaint and, on remand, the trial court is instructed to order the Contractor to file an answer to the Owners’ amended complaint.
Reversed and remanded with instructions.
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By
-
Patterson and Walter v. Clarke (Fla. 2d DCA 2024)
-
Michiko Noguchi v. Comm'r OF Internal Revenue Serv., 992 F.2d 226 (9th Cir. 1993)…ight of summons damages are deductible as “interest paid ... on indebtedness” under § 163(a) of the Internal Revenue Code. The facts of the cases are not; in dispute. They are set out fully in the opinions of the Tax Court. Midkiff v. Commissioner, 96 T.C. 724, 1991 WL 83269 (1991); Noguchi v. Commissioner, 61 T.C.M. (CCH) 2674, 1991 WL 83275 (1991). The Tax Court ruled against the taxpayers. We affirm because we agree with the Tax Court that the taxpayers never incurred an obligation to purchase the lots…
Authorities Cited
- Stacy David, Inc. v. Consuegra, 845 So. 2d 303 (Fla. 2d DCA 2003)
- Nat'l Found. for Cancer Research v. A.G. Edwards & Sons, Inc., 821 F.2d 772 (D.C. Cir. 1987)
- Green Tree Servicing, LLC v. McLEOD, 15 So. 3d 682 (Fla. 2d DCA 2009)
- Seville Condo. # 1, Inc. v. Clearwater Dev. Corp., 340 So. 2d 1243 (Fla. 2d DCA 1976)
- Bland v. Green Acres Grp., L.L.C., 12 So. 3d 822 (Fla. 4th DCA 2009)