MINNEAPOLIS AND ST. LOUIS RAILWAY
v.
COLUMBUS ROLLING MILL

U.S. | 1886-11-29
119 U.S. 149 Supreme Court of the United States (1886) Positive Treatment
Also reported at: 30 L. Ed. 376 · 7 S. Ct. 168 · SCDB 1886-028 · 1886 U.S. LEXIS 1972
Cited by 61 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

Minneapolis and St. Louis Railway sought to purchase iron rails from Columbus Rolling Mill based on an offer made by the defendant on December 8, which allowed the plaintiff to order between two thousand and five thousand tons by December 20. On December 16, the plaintiff instead ordered only twelve hundred tons, which the defendant rejected on December 18, and the plaintiff's subsequent attempt to accept the original offer on December 19 was deemed ineffectual. The Supreme Court affirmed that the plaintiff's counteroffer with different terms constituted a rejection of the defendant's original offer, and once rejected, the plaintiff could not later revive and accept the original offer without the defendant's assent.


© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.

Opinion of the Court
Me. Justice Geay,

Mr. Justice Geay,

after making tbe foregoing statement'-of the case;, delivered the opiniop. of the court.

The rules of law which govern this case are ivell settled. As no contract is complete without the mutual assent of the parties, an offer to sell imposes no obligation until it is accepted according to its terms. So long as the offer has been neither accepted nor rejected, the negotiation remains open, and imposes no obligation upon either party; the one may decline to accept, or the other may withdraw his. offer'; and either rejection or withdrawal leaves the matter as if no offer had ever been made. A proposal to accept, or an acceptance, upon terms varying from those offered, is a rejection of the offer, and puts an end to the negotiation, unless the party who made the original offer renews it, or assents to the modification suggested. The other, party, having once rejected the offer, cannot afterwards revive it by tendering an acceptance of it. Eliason v. Henshaw, 4 Wheat. 225 ; Carr v. Duval, 14 Pet. 77; National Bank v. Hall, 101 U. S. 43, 50; Hyde v. Wrench, 3 Beavan, 334; Fox v. Turner, 1 Bradwell, 153. If the offer does not limit the time for its acceptance, it must be accepted within a reasonable time. If it does, it may, at any time within the limit and so long as it remains open, be accepted or rejected by the party to whom, or be withdrawn by the party by whom, it wras made. Boston & Maine Railroad v. Bartlett, 3 Cush. 224; Dickinson v. Dodds, 2 Ch. D. 463.

The defendant, by the letter of December -8, offered to sell to the plaintiff two thousand to five thousand tons of iron rails on certain terms specified, and added that if the offer was accepted the defendant would expect to be notified prior to December 20. This offer, while it remained open, without having been rejected by the plaintiff or revoked by the defendant, would authorize the plaintiff to take at his election any number of tons not less than two thousand nor more than five thousand, on the terms specified. The offer, while unrevoked, might be accepted or rejected by the plaintiff at any time before December 20. .Instead of accepting the offer made, the plaintiff, on December 16, by telegram and letter, referring to the defendant’s letter of December 8, directed the defendant to entér an order for twelve hundred tons on the same terms. The mention, in both telegram and letter, of the date and the terms of the defendant’s original offer, shows that the plaintiff’s order was not an independent proposal, but an answer to the-defendant’s offer, a qualified acceptance of that offer, varying.the number of tons, and therefore in law a rejection of the offer. On December 18, the defendant by telegram declined to fulfil the. plaintiff’s order. The negotiation between the parties was thus closed, and the plaintiff could not afterwards’ back on the defendant’s ’original offer. The plaintiff’s attempt to do so, by the telegram of December 19, was-therefore ineffectual and created no rights against the defendant.

' Such being the legal effect of what passed in writing, between the.parties, it is unnecessary to consider whether, upon a fair interpretation of the instructions of the court, the question whether the plaintiff’s telegram and letter of December 16 ’ constituted a rejection of the defendant’s offer of December 8 ivas ruled in favor of the defendant as matter oi law, or was submitted to the jury as a question of fact. The submission of a question of law to the jury is no ground of exception if they decide it aright. Pence v. Langdon, 99 U. S. 578.

Judgment affirmed.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By (19 total)

  • Sakowitz v. Waterside Townhomes Cmty. Ass'n, Inc., 338 So. 3d 26 (Fla. 3d DCA 2022)
    …ral well-established contractual principles. It is axiomatic that an offer to form a contract only remains open for a reasonable period of time, unless the offer itself states otherwise. See Minneapolis & St. L. Ry. Co. v. Columbus Rolling-Mill Co., 119 U.S. 149, 151 (1886); see also Restatement (Second) of Contracts § 41 (2021); 1 Arthur L. Corbin, Corbin on Contracts § 2.16 (2021). Hence, in the absence of an acceptance of the offer within a reasonable period of time, there is no contract. See Minneapolis…
  • City & Cnty. of Denver v. N.Y. Tr. Co., 229 U.S. 123 (U.S. 1913)
    …e a purchase in accordance with that option, but independently of it and upon altogether different terms. Instead, therefore, of being an exercise of the option, it was a rejection of it. Minneapolis & St. Louis Railway Co. v. Columbus Rolling Mill, 119 U. S. 149, 151. The.Circuit Court of Appeals, having stated the conflicting claims of the trust company and the water company, the one that the city had elected' to purchase, and the .other that it had elected to renew, said: "The facts are stated upon which…
  • Valdes v. Larrinaga, 233 U.S. 705 (U.S. 1914)
    …d to be Assistant Secretary, and while in that position had refused to take part in the plan. His answer, which must control if - there is any difference, as the parties went ahead on it (Minneapolis & St. Louis Ry. Co. v. Columbus Rolling Mill Co., 119 U. S. 149), binds him to help in the steps to.be [*710] gone through, and in the technical part. If his help in the steps to be gone through was not to be, like the rest of his work, in the technical part alone, still there is nothing to indicate that it was…

Previewing 3 of 19 citing cases — full citator treatment, depth of discussion, and citing context are member features.