BUMBY & STIMPSON, INC., APPELLANT,
v.
PENINSULA UTILITIES CORPORATION, APPELLEE

Fla. 3d DCA | 1964-12-08
No. 64-76
Before CARROLL, HORTON and HENDRY, JJ.
169 So. 2d 499 Florida District Court of Appeal, Third District (1964) Caution
Cited by 22 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

A contractor sued for additional compensation after encountering unforeseen soft sand conditions that required substituting cast iron pipe for clay pipe and using divers for installation. The trial court directed a verdict for the defendant, and the appellate court affirmed, holding that unexpected difficulty and expense in contract performance do not entitle a contractor to additional compensation absent an enforceable modification agreement.


Holding

The court held that the trial judge correctly directed a verdict for the defendant because unexpected difficulty and expense in contract performance do not excuse the contractor from full performance under the original terms or entitle the contractor to additional compensation. The contractor bore the risk of adverse site conditions and could have protected itself through more thorough testing or anticipatory contract provisions.


Key Quotes

“It is the general rule that unexpected difficulty, expense or hardship involved in performance of a contract will not excuse the promisor from rendering due performance of his undertaking.”

Establishes the fundamental principle governing contractor liability when unforeseen conditions are encountered during performance.

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Bumby & Stimpson contracted to construct a sewage collection system for Peninsula Utilities. During performance, the contractor encountered soft sand …

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
CARROLL, Judge.

CARROLL, Judge.

This is an appeal by the plaintiff below from an adverse judgment based on a directed verdict. An amended complaint alleged that by a written contract plaintiff agreed to construct for the defendant a sewage collection system; that because of difficulties encountered it became impossible to perform certain of the work according to the original plans and specifications and that the parties orally agreed on certain changes which resulted in an additional cost to the plaintiff of $76,201.78. Recovery was sought of that amount plus an unpaid balance under the written contract, making a total $123,074.04. The amended complaint was framed in two counts. The *500first count declared on the contract.1 The second count claimed the said sum of $123,-074.04 on quantum meruit. The defendant’s answer denied liability for the additional expense, and denied it was “agreed or contemplated directly or indirectly that defendant would pay any amounts to the plaintiff except as provided in the original contract between them.” 2

Apparently with the consent of counsel, the only issue submitted to the jury was as to liability of the defendant to pay the claim of $76,201.78, representing the added expense to the contractor upon using iron pipe rather than tile, etc. After the evidence was presented the trial judge granted defendant’s motion for a directed verdict on that issue, and entered judgment for the defendant without prejudice to the plaintiff as to other amounts due under the contract. On this appeal from the judgment, the appellant contends first that it was error to direct the verdict for defendant.

The contract gave the plaintiff contractor the right to make tests to determine the physical conditions involved, and contained a recitation that the plaintiff contractor had done so.3 It was made to appear that the tests plaintiff chose to malee failed to' reveal the existence of soft sand which rendered it difficult and impracticable to use *501the dry ditch method planned for laying pipe. In certain of the areas involved the sewer pipe was to he laid below water level. The soft sand allowed flooding of the ditches. The water and the soft material which came into the ditches made it necessary to use divers to place and connect the pipe under water, and to substitute more costly cast iron pipe for the specified clay pipe. The result was increased expense in materials, labor and equipment.

When that condition became apparent the changes in method and material referred to above were suggested by the plaintiff contractor, and were consented to by defendant. There was, however, no discussion or agreement between the parties regarding any additional payment. Appellant’s contention that the original contract was abandoned and that a new contract was made is not supported by the record, which shows the work proceeded under the contract to completion, subject only to the change in the nature of the pipe and the manner of its installation. On the facts disclosed the trial judge was eminently correct in concluding that the original written contract was effective and that the defendant was not obligated to pay more than the contract required.

It is the general rule that unexpected ■difficulty, expense or hardship involved in performance of a contract will not excuse the promisor from rendering due performance of his undertaking. Tampa v. Port Tampa, Fla.App.1961, 127 So.2d 119; Simpson v. United States, 172 U.S. 372, 19 S.Ct. 222, 43 L.Ed. 482; Dermott v. Jones, 2 Wall. 1, 69 U.S., 1, 17 L.Ed. 762; Kennedy v. Reece, Cal.App., 37 Cal.Rptr. 708; Jung v. Gwin, 174 La. 111, 139 So. 774; Picard Constr. Co. v. Board of Comm’rs, 161 La. 1002, 109 So. 816; 12 Am.Jur., Contracts § 362; 6 Corbin, Contracts § 1333 (1962); Annot., 84 A.L.R.2d 12, 27 (1962). What occurred here was not impossibility of performance, as contended by appellant. The contractor could have protected itself against loss from the adverse conditions encountered, by predetermining their existence through other and more revealing tests or by an anticipatory protective provision in the contract. As stated in 6 Corbin on Contracts, supra, § 1333, p. 367:

“ * * * So, one who contracts to make a foundation or a tunnel or other excavation usually investigates for himself the character of the location, whether it be sand or solid rock or swamp or frozen mixtures, before making his estimates and offers. Therefore, the risk is usually borne by the contractor; he is not discharged from duty by actually unexpected difficulty or expense, and he has no right to extra pay for completing the job. »

A second contention made by the appellant was that the trial court “erred in usurping the plaintiff’s counsel’s presentation of plaintiff’s witnesses.” Extensive participation of the trial judge, such as by excessive questioning of witnesses, may amount to usurping the functions of counsel and be an abuse of the discretion and latitude of the court in such respects, with resultant injury to the rights of a party or parties. See, e. g., People v. Chenault, 74 Cal.App.2d 487, 169 P.2d 29, 34; Aero Enterprises, Inc. v. Walker, 123 Colo. 113, 228 P.2d 811, 815; Commonwealth v. Clairborne, 175 Pa.Super. 42, 102 A.2d 900, 904; 53 Am.Jur, Trial § 75; 28 R.C.L, Witnesses, § 180. In this case the claimed error, if any, was harmless because the principal facts which controlled the decision were not in dispute, and because any adverse effect thereof on the jury was eliminated by the direction of the verdict which relieved the jury of the need to decide the cause.

For the reasons stated, the judgment appealed from is affirmed.

Affirmed.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By (12 total)

  • N. Am. van Lines v. Collyer, 616 So. 2d 177 (Fla. 5th DCA 1993)
    …for one of the parties. Medical Center Health Plan v. Brick, 572 So. 2d 548 (Fla. 1st DCA 1990). Moreover, unexpected difficulty or expense will not excuse a party to a contract from performance. Bumby & Stimpson, Inc. v. Peninsula Utilities Corp., 169 So. 2d 499 (Fla. 3d DCA 1964). Finally, a party who, by his own acts, prevents performance of a contract provision cannot take advantage of his own wrong. Hart v. Pierce, 98 Fla. 1087, 125 So. 243 (1929); Walker v. Chancey, 96 Fla. 82, 117 So. 705 (1928). The…
  • Town OF Longboat KEY v. Carl E. Widell & SON, 362 So. 2d 719 (Fla. 2d DCA 1978)
    …t, for reasons hereinafter expressed, the contractor’s recovery is not precluded by its failure to make test bor-ings at the construction site. The town argues that this case is on all fours with Bumby & Stimpson, Inc. v. Peninsula Utilities Corp., 169 So. 2d 499 (Fla. 3d DCA 1964), which involved a contract between private parties for the laying of pipe in the construction of a sewage collection system. The contractor’s bid contemplated the use of clay pipe. Because of the existence of soft sand, the contra…
  • Dep't of Hwy. Safety & Motor Vehicles v. Pitts, 815 So. 2d 738 (Fla. 1st DCA 2002)
    …ning of witnesses, may amount to usurping the functions of counsel and be an abuse of the discretion and latitude of the court in such respects, with resultant injury to the rights of a party ...” Bumby & Stimpson, Inc. v. Peninsula Utilities Corp., 169 So. 2d 499, 501 (Fla. 3d DCA 1964). This court finds that the hearing officer below abused her discretion when she participated to the point of interposing objections to relevancy and instructing witnesses not to answer questions. (Citations to the record omi…

Previewing 3 of 12 citing cases — full citator treatment, depth of discussion, and citing context are member features.

Join FLexlaw to unlock all legal intelligence

Authorities Cited

Full citator, related cases, and AI research tools

Open in FLexlaw