H. E. CROOK COMPANY, INC.
v.
UNITED STATES

U.S. | 1926-01-25
No. 122
270 U.S. 4 Supreme Court of the United States (1926) Negative Treatment
Also reported at: 70 L. Ed. 438 · 46 S. Ct. 184 · SCDB 1925-055 · 1926 U.S. LEXIS 390
Cited by 52 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

The Supreme Court affirmed a judgment dismissing H. E. Crook Company's claim for damages resulting from Government-caused delays in completing heating system installations at a Navy Yard, holding that the contract's structure—which made the completion date provisional, reserved the Government's right to make changes and interrupt work, and tied the heating work to construction by other Government contractors—did not obligate the Government to compensate for delays beyond its control. The Court reasoned that by continuing work without protest and accepting the full contract price, the plaintiff waived any claim for delay damages that the contract itself did not expressly provide for.


© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.

Opinion of the Court
Mr. Justice Holmes

Mr. Justice Holmes delivered the opinion of the Court.

This is an. appeal from a judgment of the Court of Claims, taken under § 242 of the Judicial Code before that section was repealed by the Act of February 13, 1925, c. 229, § 13; 43 Stat. 936, 941. The claim is for damages due to delay in enabling the plaintiff to perform a contract. The Court of Claims held that the plaintiff waived any claim that it might have had by going on with the work without protest and without taking any steps to protect itself. 59 Ct. Cl. 593. The Government contends that by the terms of the'contract it was not bound to pay damages for delay.

The contract was that the plaintiff should furnish and install’ heating systems ‘ one in the Foundry Building, and one in the Machine Shop at the Navy Yard, Norfolk, Virginia.’ It allowed two hundred days from the date of delivering a copy to the plaintiff for the work to be completed. A copy was delivered on August 31, 1917, making March 19, 1918, the day for completion. But it was obvious on the face-of the contract that this date was provisional. The Government reserved the right to make changes and to interrupt the stipulated continuity of the work. Wells Brothers Co. v. United States, 254 U. S. 83, 86., The contract showed that the specific buildings referred to were in process of construction by contractors who might not keep up to time. 'The approximate contract date of completion for the foundry ’ is stated to be March 17, 1918, and that for the machine shop, February 15, 1918. The same dates were fixed for completing the heating systems, but the heating apparatus had to conform to the structure, of course, so that if the general contractors were behindhand the heating also would be delayed. They were behindhand nearly a year. When such a situation was displayed by the contract it was not to be expected that the Government should bind itself to a fixed time for the work to come to an end, and there is not a word in the instrument by which it did so, unless an undertaking contrary to what seems to us the implication is implied.

The Government did fix,the time very strictly for the contractor. It is contemplated that the contractor may be unknown, and he must satisfy the Government of his having the capital, experience, and ability to do the work. Much care is taken therefore to keep him up to the mark. Liquidated damages are fixed for his delays. But the only reference to delays on the Government side is in the agreement that if caused by its acts-they will be regarded as unavoidable, which though probably inserted primarily for the contractor’s benefit as a ground for extension of time, is not without a bearing on what the contract bound the Government to do. Delays by the building contractors were unavoidable from the point of view of both parties to the contract in suit. The plaintiff agreed to accept in full satisfaction for all work done under the contract the contract price, reduced by damages deducted for his delays and increased or reduced by the price of changes, as fixed by the Chief of the Bureau of Yards and Works. Nothing more is allowed for changes, as to which the Government is master. It would be strange if it were bound for more in respect of matters presumably beyond its control. The contract price, it is said in another clause, shall cover all expenses of every nature connected with the work to be done. Liability'was excluded expressly for utilities that the Government promised to supply. We are of opinion that the failure to exclude the present claim was due to the fact that the whole frame of the contract was understood to shut it out, although in some cases the Government’s lawyers have been more careful. Wood v. United States, 258 U. S. 120. The plaintiff’s time was extended and it was paid the full contract price. In our opinion it is entitled to nothing more.

Judgment affirmed.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By (15 total)

  • United States v. Blair, 321 U.S. 730 (U.S. 1944)
    …iling to cooperate fully in changing the contract by shortening the time provisions would be to imply a grossly unequal obligation. We cannot sanction such liability without more explicit language in the contract. Compare Crook Co. v. United States, 270 U. S. 4; United States v. Rice, 317 U. S. 61. II. The Court of Claims, in addition to awarding damages for the Government’s delay in terminating Redmon’s contract, awarded respondent $79,661.56 damages for extra labor and materials, excess wages and misce…
  • United States v. Rice, 317 U.S. 61 (U.S. 1942)
    …t the United States by the Court of Claims, 95 Ct. Cls. 84, interpreting a widely used standard form construction contract in a manner alleged to be in conflict with this Court’s interpretation of an analogous contract in Crook Co. v. United States, 270 U. S. 4. Respondent agreed to install plumbing,' heating, and electrical equipment in a Veterans’ Home to be erected at Togus, Maine, while another contractor was to do the general work of preparing the site and constructing the building. Respondent agreed…
  • …ernment for an asserted breach of a construction contract. 105 Ct. Cl. 161, 63 F. Supp. 209. We granted the Government’s petition for certiorari which alleged that the Court of Claims’ decision was in direct conflict with Crook Co. v. United States, 270 U. S. 4, and United States v. Rice, 317 U. S. 61. We hold that the Government’s contention is correct. The respondent, an electrical contractor, agreed for a fixed fee to supply the materials for and install a field lighting system at the National Airport,…

Previewing 3 of 15 citing cases — full citator treatment, depth of discussion, and citing context are member features.

Join FLexlaw to unlock all legal intelligence

Authorities Cited

Full citator, related cases, and AI research tools

Open in FLexlaw