Synopsis

This case concerns a property owner's attempt to obtain a permanent dock construction permit from the City of Port Richey. The court affirmed the denial of summary judgment because the owner failed to obtain necessary approval from the Corps of Engineers, a prerequisite for the permit.


Holding

No, the trial court did not err in denying summary judgment. A permanent permit cannot be issued without the prerequisite approval from the Corps of Engineers, which the appellant had not obtained.


Key Quotes

“The procedure specified in the ordinance requires the property owner to obtain approval of the Corps of Engineers, following the presentation of which a permanent permit shall be issued.”

Establishes the procedural requirement for obtaining a permanent permit.

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Appellant sought a permanent permit to construct a dock extending from his seawall. The City of Port Richey's ordinance requires Corps of Engineers ap…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
MANN, Judge.

*375MANN, Judge.

By ordinance the city of Port Richey provides a procedure for obtaining permits for the construction of docks. Appellant obtained a temporary permit, later can-celled, to construct a dock extending approximately 5T outward from the seawall and 16' from a platted line in the water appellant contends is his lot’s boundary. In his declaratory judgment action he sought summary judgment compelling issuance of a permanent permit. The procedure specified in the ordinance requires the property owner to obtain approval of the Corps of Engineers, following the presentation of which a permanent permit shall be issued. The ordinance provides that no construction shall be begun until a permanent permit is obtained. Appellant admits partial construction. Appellant does not allege that approval of the Corps of Engineers has been obtained. There is thus no basis for the issuance of a permanent permit.

The trial court properly denied summary judgment on the present state of the record.

Affirmed.

LILES, C. J., and ALLEN, J., concur.

ON PETITION FOR REHEARING

MANN, Judge.

Appellant asserts in his petition for rehearing that this Court has overlooked the disclaimer of interest filed by the Trustees of the Internal Improvement Fund as showing appellant’s property line to be 41 feet from the seawall as shown on the plat of Harbor Isles. We have not overlooked this fact, and agree that as between appellant and the Trustees appellant might be entitled to a finding by the trial court pursuant to FRCP 1.510(d), 31 F.S.A. that there is no dispute as to the lot line. But the appellant did not make the Trustees a party to the appeal, and the determination that the line is as he claims is not disposi-tive of the issues between appellant and the City. There is no absolute right to obtain a permit, either temporary or permanent, from the City of Port Richey, even if the dock were to be constructed entirely within appellant’s property, which he doesn’t claim. Ordinance 135 ambiguously refers, both in Section 2(a) and Section 4 to “property line” and intrusion “into the waterway.” We do not find that the interpretation of this language is before us on this record, at this stage of the case. If the appellant had made the Trustees a party appellee we would have been inclined to hold that as to them appellant was entitled, under Rule 1.510(d), to a partial summary decree fixing the lot boundary as claimed, but the notice of appeal was not served on the Attorney General. There remain issues to be tried, and the matter may now proceed toward their resolution pursuant to the applicable rules of procedure. The petition for rehearing is denied. See 6 Moore’s Federal Practice Par. 56.20; 31 F.S.A. Rule 1.510, Author’s Comment.

LILES, C. J., and ALLEN, J., concur.

Other
MANN, Judge.

MANN, Judge.

Appellant asserts in his petition for rehearing that this Court has overlooked the disclaimer of interest filed by the Trustees of the Internal Improvement Fund as showing appellant’s property line to be 41 feet from the seawall as shown on the plat of Harbor Isles. We have not overlooked this fact, and agree that as between appellant and the Trustees appellant might be entitled to a finding by the trial court pursuant to FRCP 1.510(d), 31 F.S.A. that there is no dispute as to the lot line. But the appellant did not make the Trustees a party to the appeal, and the determination that the line is as he claims is not disposi-tive of the issues between appellant and the City. There is no absolute right to obtain a permit, either temporary or permanent, from the City of Port Richey, even if the dock were to be constructed entirely within appellant’s property, which he doesn’t claim. Ordinance 135 ambiguously refers, both in Section 2(a) and Section 4 to “property line” and intrusion “into the waterway.” We do not find that the interpretation of this language is before us on this record, at this stage of the case. If the appellant had made the Trustees a party appellee we would have been inclined to hold that as to them appellant was entitled, under Rule 1.510(d), to a partial summary decree fixing the lot boundary as claimed, but the notice of appeal was not served on the Attorney General. There remain issues to be tried, and the matter may now proceed toward their resolution pursuant to the applicable rules of procedure. The petition for rehearing is denied. See 6 Moore’s Federal Practice Par. 56.20; 31 F.S.A. Rule 1.510, Author’s Comment.