FRANK J. ROONEY, INC., A FLORIDA CORPORATION, APPELLANT,
v.
CHARLES W. ACKERMAN OF FLORIDA, INC., A FLORIDA CORPORATION, APPELLEE
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
The court held that while the subcontract incorporated arbitration provisions for work within its scope, claims for extras, which were beyond the original contract scope, were not subject to arbitration and should be determined by ordinary legal remedies.
A general contractor (Rooney) and an air conditioning sub-contractor executed a subcontract that incorporated by reference the general contract and A.…
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Subcontractor Agreements cases and more on FLexlaw
This appeal involves the construction of a sub-contract to provide an air conditioning installation in an apartment project. From the record on appeal, it appears that Rooney was the general contractor engaged to construct an apartment house complex in Pinellas County. He employed the appel-lee as the air conditioning sub-contractor, and they executed a written contract which, among other things, contained the following provisions: (1) provision relative to incorporating the general contract by reference, which general contract also included by reference a printed set of provisions known as the American Institute of Architects (hereinafter, A. I. A.) general provisions;1 (2) specific provision relative to extras to the contract.2
*112Following completion of the work, the sub-contractor demanded $45,156.37 for alleged extras and demanded that this item be submitted to the American Board of Arbitration. His basis for the arbitration demand was that the arbitration clause of the A. I. A. general provisions were incorporated by reference in the general contract, and further, that the general contract was made a part of the sub-contract by reference.3 Rooney disputed this reasoning, contending that there was no general provision for arbitration; and even if there were, that the specific items for extras were excluded therefrom by the provision relative to leaving these disputes to the architect.
Rooney instituted a proceeding in the circuit court to enjoin any arbitration proceedings, which resulted in the final order here under review. The order found that the items, recovery for which was sought, were for extras [work beyond that originally entailed in the contract]. It also found that the A. I. A. general provisions relative to arbitration were incorporated in the sub-contract by reference, and that these extra items should be arbitrated, thereby disregarding the contention of Rooney that items of extras should be determined by the architect. This appeal ensued. Two points were preserved: (1) that there were no arbitration provisions in the sub-contract; (2) that if there were arbitration provisions, they did not encompass extras.
We find no merit to the first contention of the appellant. All the relevant documents were made a part of the subcontract and, as to items covered in the sub-contract [for which the sub-contractor was to receive the sum of $387,000.00], if a dispute arose he was entitled to arbitration pursuant to the A. I. A. general provisions. Quarngesser v. Appliance Buyers Credit Corp., Fla.App.1966, 187 So.2d 662; Tutko v. Banks, Fla.App.1964, 167 So.2d 110.
However, we find merit in the appellant’s second argument, which contends that the extras were not included as ar-bitrable matters because such extras go beyond the scope of the original general contract. Initially we recognize that the parties had the right to contract as they desired. S & W Motors v. Mack Trucks, Inc., Fla.App.1967, 198 So.2d 70; Howell v. Howell, Fla.App.1964, 164 So.2d 231. The sub-contractor bid the project based on the plans, specifics, general contract, addendum, etc. To perform this work, he was to be paid $387,000.00. If a dispute arose as to this work, materials, etc., he had a right to arbitration under the A. I. A. general provisions. However, the subcontract on its first page specifically provided that if he was to make a claim for extras which was above and beyond the basic sub-contract price [something that was not subject to competitive bidding], and if a dispute arose as to the amount to be charged for this work, the parties agreed that the final determination would be by the architect.4 We find the provisions of the contract relating to arbitration for those items contained in the basic agreement, and leaving the determination of extras which were items beyond the subcontract to the architect, to be valid.
It was not necessary for the parties to agree that all disputes be decided by the same authority. They had a perfect right to make a distinction between claims that would arise under the original sub-contract, the total price of which was known at the time of the execution of the contract, and to provide a different method for claims that would arise subsequent to the execution of the sub-contract and beyond the terms thereof by the very nature of their description [being extras and work per*113formed outside the terms of the sub-contract],
Therefore, we do not think that the items which were found by the trial judge to be extras [which were sought in the amount of $47,156.37 by the appellee] were subject to arbitration, and further hold that the parties should be left to their ordinary remedies for alleged breach of the contract. This is particularly so when it is remembered that, traditionally, agreements to arbitrate have been strictly construed because they have the effect of ousting a court of competent jurisdiction of the authority to determine a question initially which will arise in the future. Flaherty v. Metal Products Corp., Fla.1955, 83 So.2d 9; Fenster v. Makovsky, Fla.1953, 67 So.2d 427. It has only been since the adoption of Ch. 682 Fla.Stat. (1967), F.S.A. that these agreements have been recognized as valid in the state of Florida.
Finally, we also recognize the maxim in equity that where a party properly invokes a court’s equity powers in order to seek a declaration of his rights under a contract, such court is fully empowered to retain jurisdiction for all purposes, decide .the issues which are involved by the subject matter of the dispute, and award relief which is complete and finally disposes of the litigation. Eg., Schupler v. Eastern Mort. Co., 160 Fla. 72, 33 So. 2d 586, 590. This rule is favored because it avoids piecemeal determination of the parties’ rights, and will apply notwithstanding contractual provisions for arbitration. Cruger v. Allstate Ins. Co., Fla.App.1964, 162 So.2d 690.
Therefore, for the reasons stated, we hereby reverse the court’s order which dismissed the appellant’s complaint and direct the chancellor to proceed in order to determine the validity of the appellee’s claim.
Reversed and remanded with directions.
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By (12 total)
-
ROE v. AMICA Mut. Ins. Co., 533 So. 2d 279 (Fla. 1988)…sues and not others to submit to arbitration, and that an award would be binding only as to those issues submitted. See Pacemaker Corp. v. Euster, 357 So. 2d 208, 211 (Fla. 3d DCA 1978); Frank J. Rooney, Inc. v. Charles W. Ackerman of Florida, Inc., 219 So. 2d 110, 112 (Fla. 3d DCA), cert, dismissed, 230 So. 2d 13 (Fla. 1969). He contends, however, that the issue of damages with respect to amount cannot be so divided and parties must arbitrate total damages or none at all. We are not persuaded by the logic or…
-
Damora v. Stresscon Int'l, Inc., 324 So. 2d 80 (Fla. 1975)…olidated Grocery Co., [80 Fla. 531, 86 So. 431]; and 6 C.J.S., Arbitration and Award, § 29.” [Emphasis supplied] See also Flaherty v. Metal Products Corporation, 83 So. 2d 9 (Fla.1955); Prank J. Rooney, Inc. v. Charles W. Ackerman of Florida, Inc., 219 So. 2d 110 (Fla.App.3d 1969). We hold that an agreement to arbitrate future disputes in another jurisdiction is outside the authority of the Florida Arbitration Code, Chapter 682, Florida Statutes, and such a provision renders the agreement to arbitrate voida…
-
Pacemaker Corp. v. Euster, 357 So. 2d 208 (Fla. 3d DCA 1978)…y of those controversies or disputes which the parties have agreed to submit to arbitration. Wood-Hopkins Contracting Co. v. C. H. Barco Contracting Co., Inc., 301 So. 2d 479 (Fla. 1st DCA 1974); Frank J. Rooney, Inc. v. Charles W. Ackerman of Fla., 219 So. 2d 110 (Fla.3d DCA 1960). The motion of the defendant for the arbitration to be restricted to that which was expressly contracted for should have been granted, and the order appealed from is reversed to the extent that it made provision for the arbitratio…
Previewing 3 of 12 citing cases — full citator treatment, depth of discussion, and citing context are member features.
Join FLexlaw to unlock all legal intelligenceAuthorities Cited
- Cruger v. Allstate Ins. Co., 162 So. 2d 690 (Fla. 3d DCA 1964)
- Schupler v. E. Mortg. Co., 160 Fla. 72 (Fla. 1948)
- Howell v. Howell, 164 So. 2d 231 (Fla. 2d DCA 1964)
- Fenster v. Makovsky et ux., 67 So. 2d 427 (Fla. 1953)
- Flaherty v. The Metal Prods. Corp., 83 So. 2d 9 (Fla. 1955)
- Quarngesser v. Appliance Buyers Credit Corp., 187 So. 2d 662 (Fla. 3d DCA 1966)
- Tutko v. Clyde M. Banks, 167 So. 2d 110 (Fla. 3d DCA 1964)
- S & W Motors v. Mack Trucks, Inc., 198 So. 2d 70 (Fla. 1st DCA 1967)