ADOBE BRICK AND SUPPLY COMPANY, APPELLANT,
v.
PORT ROYALE APARTMENTS, INC., AND FIRST GENERAL CONTRACTORS, INC., APPELLEES

Fla. 3d DCA | 1972-10-10
No. 72-389
Before BARKDULL, C. J., and CHARLES A. CARROLL and HAVER-FIELD, JJ.
267 So. 2d 336 Florida District Court of Appeal, Third District (1972)

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

A supplier of drywall materials (Adobe Brick) sought to enforce a mechanic's lien against property owner Port Royale Apartments and contractor First General Contractors. The trial court found $11,697.26 due to the supplier and affirmed that judgment, rejecting claims for materials delivered after the lien filing date and finding the payment amounts were supported by evidence.


Holding

The trial court's finding that $21,000 was paid on August 8, 1970, was supported by competent substantial evidence and not contrary to the weight of the evidence. The rejection of evidence for materials delivered after November 8, 1970, was not reversible error based on the court's earlier ruling denying amendment of the complaint and lien claim. The judgment for $11,697.26 was affirmed.


Headnotes

[1] A trial court's finding of fact regarding the amount paid to a claimant is supported by competent substantial evidence if the evidence is in conflict and the finding is s…

[2] A trial court's refusal to allow recovery for materials delivered after the date specified in a claim of lien is not reversible error if the court previously ruled that s…

Previewing 2 of 3 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Key Quotes

“That finding of the trial court is not shown to be contrary to the weight of the evidence. The evidence as to the amount so paid was in conflict, and the court's finding thereon is supported by competent substantial evidence in the record.”

Establishes the standard of review for factual findings in mechanic's lien cases—a finding supported by competent substantial evidence will not be reversed despite conflicting evidence.

Previewing 1 of 2 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Adobe Brick and Supply Company supplied drywall materials to First General Contractors, a subcontractor working on Port Royale Apartments property. Th…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
PER CURIAM.

PER CURIAM.

This appeal is by the plaintiff below from-.the final judgment entered in a mechanic’s lien- foreclosure action. The- ap*337pellant Adobe Brick and Supply Company, herein referred to as the claimant, was a supplier of materials to a subcontractor, the appellee First General Contractors, Inc., herein referred to as the contractor. The appellee Port Royale Apartments, Inc. was the owner of the property involved.

Plaintiff’s action was predicated on a filed claim of lien dated December 22, 1970, for “furnished labor, services or materials,” wherein it was recited that the materials delivered consisted of “Drywall Materials.” Therein it was stated that the unpaid balance was $29,842, and that the last date upon which materials were furnished was November 8, 1970.

On final hearing the court held there was due to the plaintiff lien claimant the sum of $11,697.26, and granted judgment therefor against the owner, the contractor and the obligor on the bond to which the lien had been transferred. Jurisdiction was reserved to later award judgment for attorney fees for the claimant, and costs.

The appellant presents four contentions. First, that the trial court committed error in arriving at the balance held due to the claimant by finding that $21,000 was paid to claimant on or about August 8, 1970, it being the position of the appellant that only $7,000, or at the most $14,000 was paid to it on that occasion. Without observing a need to discuss this point in detail, we hold the contention is without merit. That finding of the trial court is not shown to be contrary to the weight of the evidence. The evidence as to the amount so paid was in conflict, and the court’s finding thereon is supported by competent substantial evidence in the record.

The second and third contentions relate to refusal of the court to allow recovery of $3,517.12 for materials which were delivered by the claimant to the contractor after November 8, 1970. Prior to plaintiff’s offer of evidence thereof at trial the court had denied plaintiff’s motion for leave to amend the complaint incident thereto, and for leave to file an amended claim of lien specifying December 8, 1970, as the last date of which materials were delivered, and on pretrial hearing had ruled that such evidence would not be admitted. Those rulings were not assigned as error on appeal.

Without expressing a view on the correctness or incorrectness of said unchallenged rulings of the trial court, we hold that based on those rulings it was not reversible error for the court to reject the proffered evidence of materials delivered after November 8, 1970.

The remaining contention of the appellant has been considered in the light of the record and briefs and is found to be without merit.

Affirmed.


Cases With Similar Vibessemantic neighbors from the corpus

Full citator, related cases, and AI research tools

Open in FLexlaw