Synopsis

Affirmed judgment for Morgan Construction's damages for lost profits where Cement Roofing prevented issuance of a building permit by failing to timely perform a condition precedent, constituting breach of contract under the prevention doctrine.


Holding

A party's prevention or hindrance of a condition precedent to contract performance constitutes a breach of contract unless the prevention is caused by the other party's conduct or the contract allocates that risk.


Headnotes

[1] A party's prevention or hindrance of a condition precedent to contract performance constitutes a breach of contract entitling the other party to damages for lost profits,…

Previewing 1 of 1 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Key Quotes

“Prevention or hindrance by a party to a contract of any occurrence or performance requisite under the contract for the creation or continuance of a right in favor of the other party, or the discharge of a duty by him, is a breach of contract, unless (a) the prevention or hindrance is caused or justified by the conduct of the other party, or (b) the terms of the contract are such that the risk of such prevention or hindrance as occurs has been assumed by the other party.”

Restatement, Contracts § 315(1) establishing the prevention doctrine

Facts & Procedural History

Morgan Construction agreed to construct a building for Cement Roofing Industries. Morgan was ready to perform but was denied a building permit because…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
MANN, Chief Judge.

MANN, Chief Judge.

Morgan Construction Company of Tampa agreed to construct a building for Cement Roofing Industries, Inc. It was ready to perform but was denied a building permit because of Cement Roofing’s failure to perform timely a condition precedent to its issuance. These facts found by the trial judge are supported by substantial, competent evidence. Morgan sued for and got damages for loss of profit on the contract.

Restatement, Contracts § 315(1) states:

(1) Prevention or hindrance by a party to a contract of any occurrence or performance requisite under the contract for the creation or continuance of a right in favor of the other party, or the discharge of a duty by him, is a breach of contract, unless
(a) the prevention or hindrance is caused or justified by the conduct of the other party, or
(b) the terms of the contract are such that the risk of such prevention or hindrance as occurs has been assumed by the other party.

The trial judge explained his ruling in a well reasoned order, citing numerous cases. See also Sharp v. Williams, 1939, 141 Fla. 1, 192 So. 476; Continental Casualty Company v. Reddick, Fla.App.1st 1967, 196 So.*582d 239; Keystone Acceptance Corp. v. Dynalectron Corp., 1971, 144 U.S.App.D.C. 253, 445 F.2d 729; 6 Corbin, Contracts § 1264.

Affirmed.

HOBSON and BOARDMAN, JJ„ concur.