SOUTHEASTERN BUILDERS, INC. OF ALABAMA, APPELLANT,
v.
JOE BRASHEARS STEEL, INC., APPELLEE
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
A general contractor appeals a directed verdict awarding a steel supplier the full contract price of $41,374.41, arguing it should have been permitted to offset the supplier's damages for delays, improper sequencing, and defective materials. The court holds that while delay damages are barred by contract, damages from defective and nonconforming materials are not, and reverses for trial on the contractor's counterclaim.
The contractor's damages for delays in delivery and improper sequencing are properly barred by the contract's 'no damages for delay' clause, but the trial court erred in using that clause to foreclose the contractor's claim for damages caused by delivery of defective and nonconforming materials, since such damages result from the defect itself, not merely from delivery delay. The case is reversed for trial on the contractor's counterclaim for damages from defective materials.
[1] A trial court may permit proof of a contractor's asserted setoff against a supplier's claim, even without an explicit counterclaim, absent demonstrated prejudice to the s…
[2] Acceptance of materials upon delivery may constitute a waiver of claims for damages on account of delay in delivery, as specified in a contract.
Previewing 2 of 5 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.
Join FLexlaw to unlock all legal intelligence“The trial court erred, however, in holding that the quoted clause forecloses the contractor's claim for damages caused by delivery of defective and nonconforming materials. Although construction delay was a result of delivering faulty steel, delay itself was not the default complained of.”
Establishes the key distinction between damages barred by the no-damages-for-delay clause and damages recoverable for defective materials themselves.
Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.
Join FLexlaw to unlock all legal intelligenceSoutheastern Builders, as general contractor for a Sears Roebuck building in Pensacola, contracted with Joe Brashears Steel for structural steel. The …
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Counterclaim For Damages cases and more on FLexlaw
SMITH, Judge.
The general contractor for construction of a Sears Roebuck building in Pensacola refused to pay for structural steel furnished the project. The supplier sued the contractor and the court directed a verdict for the supplier in the amount of the contract price. The jury’s verdict added the amount of certain disputed extras. The contractor asserts on appeal that the trial court erred in directing a verdict for the contract price of $41,374.41 and in refusing to permit the jury to assess, as a setoff reducing its liability to the supplier, the contractor’s damages sustained as a result of the supplier’s delays in furnishing the steel, its failure to deliver sequentially the types of steel needed for continuous construction and its furnishing of steel which was defective or did not conform to specifications.
The case reached trial without issues clearly pleaded between supplier and contractor. Notwithstanding the absence of a counterclaim, the contractor was permitted over objection to introduce evidence of the supplier’s claimed inadequacies in performance and of the contractor’s damages. While the contractor’s setoff should have been explicitly pleaded as a counterclaim, Ocean Ridge Devel. Corp. v. Quality Plastering, Inc., 247 So. 2d 72 (Fla.App. 4th, 1971), we conceive that the trial court acted within its discretion, in the absence of demonstrated prejudice to the supplier, in permitting proof of the contractor’s asserted setoff against the contract price. Rules 1.170, 1.190(b), R.C.P. After thus permitting full development of the contractor’s asserted setoff, the trial court ruled as a matter of law that the contractor’s damages resulting from delay in the delivery of steel and from the supplier’s departure from desirable delivery sequences were not recoverable. The supplier’s bid forms, which formed a part of the contract, specified that acceptance of deliveries would constitute waiver of claims for delay in delivery.1 The trial court did not err in giving that provision effect notwithstanding the supplier’s stated “anticipation” of meeting a more rapid delivery schedule. Nor did the trial court err in eliminating the contractor’s asserted dam ages arising from the absence of sequential delivery, to which the supplier did not assent in the exchange of contract documents.
The trial court erred, however, in holding that the quoted clause forecloses the contractor’s claim for damages caused by delivery of defective and nonconforming materials. Although construction delay was a result of delivering faulty steel, delay itself was not the default complained of. Delays which were subject to the disclaimer of liability were delays in delivery, acceptance of which might reasonably be regarded as waiver. But the “no damages for delay clause” cannot reasonably be held to foreclose claims resulting from delay not incurred at delivery, when the fact and extent of future delay, attending correction or replacement of materials found to be defective, might be unknown or incalculable. See Wood v. Ft. Wayne, 119 U.S. 312, 322, 7 S.Ct. 219, 224, 30 L.Ed. 416, 420 (1886).
On remand of the case, the verdict liquidating the principal amount owed the supplier need not be disturbed, but the parties by proper pleadings should establish issues to be tried on the contractor’s counterclaim for damages caused by the supplier’s delivery of defective and nonconforming materials.
REVERSED.
RAWLS, Acting C. J., and McCORD, J., concur. . “Seller shall not be responsible for delays arising from causes beyond its reasonable control and shall be responsible only for failure to make reasonable effort in pursuance of its performance, provided, however, that acceptance of materials on delivery shall constitute a waiver of any claims for damages on account of delay.”
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By
-
Motorola Commc'ns & Elecs., Inc. v. Nat'l Patient Aids, Inc., 427 So. 2d 1042 (Fla. 4th DCA 1983)…r notice of appeal. . As to the filing of a counterclaim with which to allege a set-off, see Ocean Ridge Development Corp. v. Quality Plastering, Inc., 247 So. 2d 72 (Fla. 4th DCA 1971); and Southeastern Builders, Inc. v. Joe Brashears Steel, Inc., 336 So. 2d 1228 (Fla. 1st DCA 1976). . Section 679.507(1), Florida Statutes (1977), provided: If it is established that the secured party is not proceeding in accordance with the provisions of this part disposition may be ordered or restrained on appropriate term…
-
Sunrise Point, Inc. v. Reliance Realty, Inc., 371 So. 2d 674 (Fla. 3d DCA 1979)…the defendant was entitled to recovery for breaches of the same contract by the plaintiff. Our review of the record convinces us that there is no inconsistency in the verdict. Cf. Southeastern Builders, Inc. of Alabama v. Joe Brashears Steel, Inc., 336 So. 2d 1228, 1230 (Fla. 1st DCA 1976). We have examined the other points presented by the appellant and have found them not to present error. The cross-appeal asks us to examine the evidence upon the basis that there is no rational explanation for the amount a…
Authorities Cited
- Bryant v. Brinkley, 247 So. 2d 72 (Fla. 1st DCA 1971)
- Wood v. Fort Wayne, 119 U.S. 312 (U.S. 1886)