NORIN MORTGAGE CORP., A DELAWARE CORPORATION, AUTHORIZED TO DO BUSINESS IN THE STATE OF FLORIDA, APPELLANT,
v.
WASCO, INC., A FLORIDA CORPORATION, APPELLEE

Fla. 2d DCA | 1977-03-16
No. 76-1080
McNULTY, A. C. J., and SCHEB, J., concur.
343 So. 2d 940 Florida District Court of Appeal, Second District (1977) Positive Treatment
Cited by 10 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

Norin Mortgage Corp. appeals a judgment awarding Wasco, Inc. payment for construction work performed under a development project. The court affirmed the trial court's finding that privity existed between Norin and Wasco, but reversed on three issues regarding the calculation of damages: the date interest began accruing, the recoverability of certain litigation costs, and a deduction for warranty obligations.


Holding

Privity existed between Norin and Wasco, and Norin was obligated to pay the balance owed by Blount. However, interest should accrue from March 11, 1975 (the date of final submission of affidavit), not January 20, 1975. Norin is not liable for the $1,521.19 in damages consisting of interest on amounts owed to subcontractors and costs of defending subcontractor suits. The $5,600 deduction for warranty obligations was improper.


Headnotes

[1] Privity of contract may exist between a lender and a contractor when the contractor incurs additional obligations in exchange for the lender's guarantee to set aside fund…

[2] Interest on a contract balance begins to accrue on the date the contractor submits a final affidavit for payment, not on the date of substantial completion certification.

Previewing 2 of 4 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Key Quotes

“there is sufficient evidence in this record to support the court's conclusion that privity existed between Wasco and Norin to the extent that Norin was obligated to pay the balance owed by Blount under the construction contract”

Establishes the core holding that privity existed between the parties despite the three-party contractual structure.

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Norin loaned Blount Development Company $2,120,000 for a construction project. Blount contracted with Wasco to construct buildings for $1,451,000. Was…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
GRIMES, Judge.

GRIMES, Judge.

This is an appeal and a cross-appeal from a judgment entered in a dispute between Norin Mortgage Corp. (Norin) and Wasco, Inc. (Wasco), the contractor. Norin entered into a loan agreement with Blount Development Company whereby No-rin agreed to loan Blount $2,120,000. Blount entered into a contract with Wasco in which Wasco agreed to build certain buildings contemplated by the construction loan agreement for $1,451,000. Wasco fully performed the construction required under its contract, but Blount failed to pay Wasco $147,903. Blount also defaulted in its obligations to Norin, which resulted in the foreclosure of Norin’s mortgage with Norin bidding in at the sale.

Wasco sued Norin for the balance owed to it by Blount on the theory that Wasco had incurred certain additional obligations by signing an addendum to the loan agreement in exchange for a guarantee by Norin that it would set aside funds from the Blount loan to pay Wasco for the performance of its construction contract. Since the language of the pertinent documents and the relationship of the parties are peculiar to this case, we think it unnecessary to discuss the facts in further detail. Suffice it to say, we have concluded that there is sufficient evidence in this record to support the court’s conclusion that privity existed between Wasco and Norin to the extent that Norin was obligated to pay the balance owed by Blount under the construction contract.

However, there are three minor aspects of the case in which we believe the court erred and to which we will briefly refer. First, the court held that Norin became obligated to pay Wasco on January 20, 1975, which was the date Wasco received a letter from the architect certifying substantial completion of Wasco’s work. Consequently, interest upon the contract balance was determined to run from that date. We think the earliest date upon which the interest could begin to run was March 11, 1975, which was the date Wasco submitted its final affidavit to Blount under Section 713.06(3)(d)l, Florida Statutes (1973).

In the second place, we believe the court improperly held Norin liable for $1,521.19 in damages consisting of interest on money owed by Wasco to its subcontractors together with the expense of attorneys’ fees and court costs which Wasco must indemnify its bonding company for defending suits brought by the subcontractors for monies owed by Wasco in connection with the job. That portion of the award representing interest can easily be disposed of when it is realized that this item of damage is already included as part of the interest on the contract sum being recovered from Norin. The cost of defending the subcontractor’s suits presents a closer question.

The general rule concerning recovery of expenses of litigation as consequential damages for breach of contract is stated in 5 Corbin on Contracts, § 1037 (1964), as follows:

“. . . If the plaintiff [Wasco] can show that the defendant’s [Norin’s] breach of contract has caused litigation involving the plaintiff [Wasco] in the payment of counsel fees, court costs, and the amount of a judgment, and shows further that such expenditure is reasonable in amount and could not have been avoided by him by reasonable and prudent effort, he can recover damages against the defendant [Norin] measured by the amount of these expenditures.

Corbin goes on to explain that cases to which the rule of this section is most commonly applied are actions for breach of warranty where party A sells defective goods to party B with an express or implied warranty of kind or quality with reason to know that B will resell the goods to a new purchaser with a similar warranty. When B resells the goods to party C and C sues B, B is entitled to recover as an element of damage from A the cost of defending C’s suit. We have been unable to find a case on point nor has any authority been cited to us for the proposition that because one is expecting to pay another out of money he is rightfully entitled to receive, he is then able to recover the cost of defending an action brought by his creditor from the person who should have paid him sooner. Perhaps one reason for the lack of such a precedent is explained by a caveat to the general rule which provides that in any event an expense of litigation cannot be recovered if the plaintiff (Wasco) had no defense in that litigation and knew it. Corbin, supra. Presumably, Wasco owed the money to the subcontractors and simply employed counsel to defend the actions in the hope that by the time judgments were obtained Wasco would have received its payment from Blount or Norin. Be that as it may, in the absence of precedent, we are reluctant to permit damages of this nature because we can foresee that our ruling might have the effect of promoting a multitude of commercial litigation in which one who is waiting to be paid could later claim that he is entitled to recover from his payor the cost of defending various suits of his creditors.

We also think the court erred in deducting from monies owed by Norin to Wasco the sum of $5,600 which was determined to represent the value of the one year guarantee to correct defects contained in the construction contract. The evidence upon which this figure was based came from an architect who testified as an expert witness that this was the reasonable value of the work which would customarily be required under a contract of this size. However, Wasco did do some corrective work after the issuance of the architect’s certificate. Furthermore, this suit was tried more than a year after Wasco’s work was completed, and there is no indication that Wasco was ever notified that any other corrective work was needed. Even if further corrective work had been required, the need for notifying Wasco has practical significance. Wasco explained that it had performed the bulk of the job through subcon tractors and that had Wasco been notified that further corrective work was needed, it would have been in a position to obtain the performance of the corrective work by the applicable subcontractor. Finally, since Blount first breached its contract by failing to pay Wasco the balance owed for its construction work, we doubt that Blount could have thereafter forced Wasco to perform any subsequent corrective work, and for purposes of this claim, Norin would stand in the shoes of Blount. See Carr v. Stockton, 84 Fla. 69, 92 So. 814 (1922).

Except as set forth above, the judgment is affirmed, but the case is remanded for the entry of an amended judgment which will reflect the changes required by this opinion.

McNULTY, A. C. J., and SCHEB, J., concur.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • Acquisition Corp. OF Am. & Kenneth v. Hemmerle, Sr., 543 So. 2d 878 (Fla. 4th DCA 1989)
    …onditioning, Inc., 353 [*883] So. 2d 840 (Fla.1977). That being the case, expenses connected with such litigation are not recoverable. ABD Management v. Robert L. Turchin, Inc., 490 So. 2d 202 (Fla. 3d DCA 1986); Norin Mortgage Corp. v. Wasco, Inc., 343 So. 2d 940 (Fla. 2d DCA 1977). In addition, by far the vast majority of the fees claimed by Coffman resulted from the prosecution of its claim against Hemmerle. Coffman claims that these fees should be recoverable because of Hemmerle’s “wrongful act” of breac…
  • ABD Mgmt. Corp. v. Robert L. Turchin, Inc., 490 So. 2d 202 (Fla. 3d DCA 1986)
    …ioning, Inc., 353 So. 2d 840 (Fla.1977) (owner’s payment to general contractor is not ordinarily a condition precedent to right of subcontractors to receive payment from general contractor for work completed) and Norin Mortgage Corp. v. Wasco, Inc., 343 So. 2d 940 (Fla. 2d DCA 1977) (construction contractor could not recover attorney’s fees and costs which it incurred in connection with defending suits which had been brought against contractor by subcontractors for money owed by the contractor which had not b…
  • Butler Plaza, Inc. v. Allen Trovillion, Inc., 389 So. 2d 682 (Fla. 5th DCA 1980)
    …architect) was submitted to Butler. Similarly, payment for work done beyond the scope of the written contract was due after it was completed and after demand or request for payment by Trovil-lion was made.2 See Norin Mortgage Company v. Wasco, Inc., 343 So. 2d 940 (Fla. 2d DCA 1977). For “extra” contract work, particularly where no set amount was agreed to by the parties, completion of the work alone could not make the sums “due” because the obligor (here Butler) had no idea what amount to pay, nor when, abse…

Previewing 3 of 5 citing cases — full citator treatment, depth of discussion, and citing context are member features.