DEAN REFRAM ET AL., APPELLANTS,
v.
JAMES PORTER AND MARTHA PORTER, APPELLEES

Fla. 2d DCA | 1977-03-30
No. 76-973
McNULTY and SCHEB, JJ., concur.
343 So. 2d 1343 Florida District Court of Appeal, Second District (1977) Positive Treatment
Cited by 7 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.


Holding

The court held that the stipulated sum was part of the purchase price, not an unenforceable penalty, and a vendor's lien was properly imposed.


Headnotes

[1] A stipulated sum in a contract for failure to timely complete a golf course, which was part of the consideration for a reduced purchase price, is not an unenforceable pen…

[2] The intent of the parties is a key factor in determining whether a stipulated sum constitutes liquidated damages or an unenforceable penalty.

Previewing 2 of 5 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Buyers and sellers entered a contract for real property where buyers agreed to build a golf course within a certain time or pay an additional sum. Sel…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
BOARDMAN, Chief Judge.

BOARDMAN, Chief Judge.

Appellants/defendants appeal the final judgment entered in favor of appel-lees/plaintiffs in a suit for payment of the full purchase price of and a vendor’s lien on a parcel of real property. Appellants/buyers and appellees/sellers entered into a written contract for sale of realty on which appellants planned to construct a golf course. The pertinent part of the contract provided that:

In addition to the aforesaid purchase price, Buyer guarantees to the Sellers that he or his assigns will begin construction of an 18-hole regulation par 71 or 72 golf course at least 6,800 yards in length measuring from championship tees to the middle of the greens, to be approved by the United States Golfers Association within one (1) year from the date of closing and to be completed within twenty-four (24) months from closing. The guarantee contained in this paragraph will survive the closing. A default by the Buyer in failing either to commence construction or to complete construction of the golf course as specified herein shall be an event of default entitling the Sellers to a penalty of an additional cost of $250.00 per acre on the entire 460 acre purchase, or a total penalty of $115,000.00 payable within ninety (90) days of such default, it being understood by and between the parties that part of the consideration for the purchase of said property is the construction of the aforesaid golf course (the promise to construct same on the part of the Buyer resulted in the Sellers reducing the purchase price of the above described property by $250.00 per acre).

Likewise, all prices per acre for the lands set forth in the options in paragraph 2 below shall be increased by $250.00 per acre for the same reasons set forth above, anything hereinafter set forth to the contrary notwithstanding.

The sellers alleged in their complaint that the buyers did not perform according to the terms of this provision, that is to complete the construction of a golf course within two years of the closing. The buyers alleged in their answer and affirmative defense that the golf course was completed or substantially completed as contemplated by the contract. After a hearing the trial judge ruled that the sum the parties agreed to in the contract was not a penalty but was a part of the purchase price and that appel-lees were entitled to $115,000 plus interest, plus costs. A vendor’s lien was imposed on the property.

The sole meritorious point raised by appellants is whether the amount stipulated by the contract in the event of default constituted an unenforceable penalty. Appellants assume that the agreement to pay an additional $250 per acre for failure to timely complete the golf course is in the nature of damages for breach of contract. We do not agree. We submit, however, that even if the stipulation were included to provide for damages for breach of contract, it would not be a penalty but would be liquidated damages. While there is no general rule to determine whether a sum stipulated for breach of contract is a penalty, the courts will consider the reasonableness of the provision, the certainty of establishing actual damages, and the intent of the parties. See 9 Fla.Jur. Damages §§ 103, 104 (1956, Supp.1976).

In consideration of the value of the property reflected by other offers which were higher than the offer accepted by appellees, a $250 per acre increment to a base price of $1350 per acre would not be unreasonable. Testimony introduced at trial, particularly that regarding the parties’ negotiations, established that both appellants and appellees were fully cognizant of the purpose of the provision requiring timely construction of a golf course. Appellees planned to retain the property surrounding the parcel sold to appellees. Their agreement to sell the property to appellants at a lower price per acre was directly dependent on the development of a golf course which they believed would provide a hedge against the possibility of a recession and consequent decrease in property value. In the event of a breach, calculation of damages would be speculative and uncertain. It would be extremely difficult to gauge the effect a completed, partially completed, or nonexistent golf course would have on the surrounding property value.

This stipulation is not, however, a damage provision for breach of contract, and the sellers did not bring this action for damages. They were seeking payment of the unpaid purchase price. The purchase price is clearly set out in the contract, that is $610,000 plus a golf course or $610,000 plus $115,000. From a reading of the contract the intent of the parties is clear. They agreed to a purchase price of $1600 per acre. In reliance on and in consideration of the completion of a golf course by December 21,1974, the purchase price to be paid in cash was $1350 per acre. See Cox v. Smith, 93 Ark. 371, 125 S.W. 437 (1910).

Accordingly a vendor’s lien was properly imposed on the property to secure the unpaid alternate purchase price of $115,000. See Oliver v. Mercaldi, 103 So. 2d 665 (Fla.2d DCA 1958).

The findings of the trial court are accorded a presumption of correctness and will not be disturbed on review by this court where, as here, there is sufficient, competent evidence to support those findings.

AFFIRMED.

McNULTY and SCHEB, JJ., concur.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • Prime Homes, Inc. v. Pine Lake, LLC, 84 So. 3d 1147 (Fla. 4th DCA 2012)
    …erefore, affirm as to this point. Next, we consider the propriety of the vendor’s lien that the trial court imposed against the property. A vendor’s lien is placed on property to secure an unpaid amount of the purchase price. See Refram v. Porter, 343 So. 2d 1343, 1345 (Fla. 2d DCA 1977). Vendor’s liens arise through agreements for deed, as the vendor essentially holds title to the property to secure payment of the agreed upon purchase price. Jasper v. Orange Lake Homes, Inc., 151 So. 2d 331, 333 (Fla. 2d DC…
  • Secrist v. Nat'l Serv. Indus., Inc., 395 So. 2d 1280 (Fla. 2d DCA 1981)
    …f the provision calls for an amount in damages that is excessive or unreasonable, and hence a penalty, the provision will not be enforced by the courts. See Poinsettia Dairy Products v. Wessel Co., 123 Fla. 120, 166 So. 306 (1936); Refram v. Porter, 343 So. 2d 1343 (Fla.2d DCA 1977). In such a case, the plaintiff may recover only the actual damages which were pled and specifically proven at trial. Poinsettia Dairy Products v. Wessel Co., supra. Secrist contends that although the final judgment first states th…
  • T.A.S. Heavy Equip., Inc. v. Delint, Inc., 532 So. 2d 23 (Fla. 4th DCA 1988)
    …. Hyman v. Cohen, 73 So. 2d 393 (Fla.1954). In making this determination the courts will usually consider (1) the reasonableness of the provision, (2) the certainty of establishing actual damages, and (3) the intent of the parties. Refram v. Porter, 343 So. 2d 1343 (Fla. 2d DCA 1977). In the final analysis the test is whether the damages flowing from the breach are readily ascertainable at the time the contract is executed. South Florida Regional Planning Council v. Board of County Commissioners of Palm Beach…

Previewing 3 of 4 citing cases — full citator treatment, depth of discussion, and citing context are member features.

Join FLexlaw to unlock all legal intelligence

Authorities Cited

Full citator, related cases, and AI research tools

Open in FLexlaw