KONSLER STEEL COMPANY, PETITIONER,
v.
JOHN PARTIN, RESPONDENT

Fla. | 1978-02-20
No. 50238
ADKINS, ENGLAND, SUNDBERG and KARL, JJ., concur., OVERTON, C. J., and BOYD, J., dissent., OVERTON, C. J., and ADKINS, ENGLAND, SUNDBERG, HATCHETT and KARL, JJ., concur.
356 So. 2d 264 Florida Supreme Court (1978) Positive Treatment
Cited by 10 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

Konsler Steel Company, a materialman who supplied materials to a construction project, failed to provide timely notice to the property owner as required by Florida's Mechanic's Lien Law but filed a lien claim within 90 days. The Florida Supreme Court held that the materialman could recover from improper final payments made by the owner despite the late notice, reversing the Fourth District Court of Appeals.


Holding

A materialman's failure to provide timely preliminary notice does not prevent recovery from improper final payments made by an owner who violates the statute by failing to obtain a contractor's affidavit and retain the required final payment. The materialman can recover the amount of improper payments, limited to the difference between what should have been retained and what was actually retained.


Headnotes

[1] A materialman who fails to furnish timely notice to the owner but files a claim of lien and furnishes notice within 90 days from the last furnishing of materials may shar…

[2] Strict compliance with the Mechanic's Lien Statute is not always an indispensable prerequisite to seeking affirmative relief thereunder.

Previewing 2 of 5 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Key Quotes

“while a notice to the owner given in compliance with the time limitations provided in Section 713-06(2)(a) placed the lienor in a priority position, such a notice given after the expiration of the 45-day period could be the basis for perfecting a valid lien provided such notice was given within the requisite 90-day period and before the owner has properly paid that portion of the sums due under the direct contract to which such lienor would be entitled.”

Establishes that late notice within 90 days can still perfect a valid lien for recovery purposes, even if it loses priority status.

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

Konsler Steel supplied materials to a construction project between June 7-13, 1974, but was never compensated by the contractor. On September 5, 1974,…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
HATCHETT, Justice.

HATCHETT, Justice.

This case involves the operation of Florida’s Mechanic’s Lien Law, Chapter 713, Florida Statutes. The question we must decide is whether a materialman who fails to furnish timely notice to owner, but who nevertheless files a claim of lien and furnishes notice within 90 days from the date he last furnished materials, is entitled to share in a final payment improperly made by the owner by virtue of the owner’s failure to obtain a contractor’s affidavit. The Fourth District Court of Appeals answered this question in the negative in a decision reported at 336 So. 2d 684 (Fla.4th DCA 1976). That decision directly conflicts with Crane Co. v. Fine, 221 So. 2d 145 (Fla.1969). Jurisdiction vests pursuant to Article V, Section 3(b)(3), Florida Constitution. We reverse.

The facts are as follows: Respondent is the owner of property who contracted to have a building constructed on his property by a person not a party to this litigation and who will hereinafter be referred to as ‘contractor.’ Petitioner, Konsler Steel Company, was a supplier of materials to the job between June 7 and June 13, 1974, but was never compensated for those materials by the contractor. Consequently, on September 5, 1974, petitioner filed a claim of lien against respondent’s property in the amount of $6,415. Preliminary notice to owner was mailed the same day. The claim was filed within 90 days from the final furnishing of material as is required by Section 713.08(5). Preliminary notice, however, was not made within the statutory time frame. Section 713.06(2)(a) states:

. notice must be served before commencing or not later than 45 days from commencing to furnish his services or materials .

Prior to receipt of notice, respondent paid all sums due under the contract except $1,164.46. Final payment was made without obtaining the statutorily required contractor’s affidavit. See Section 713.-06(3)(d)(l).

After receipt of notice, respondent paid to petitioner the remaining $1,164.46 and filed suit to cancel its lien. Petitioner counterclaimed for foreclosure and both parties moved for summary judgment. The trial judge ruled in favor of petitioner and ordered foreclosure. The Fourth District Court of Appeal reversed, holding that petitioner’s failure to comply with Section 713.-06(2)(a) prevented perfection of the lien. The Court further held that “ . strict compliance with the Mechanic’s Lien Statute is an indispensible prerequisite to seeking affirmative relief thereunder.” Partin v. Konsler Steel Company, supra, at 685.

We reverse the opinion of the District Court and adopt the opinion of the trial judge, which in essential part states:

Neither the Plaintiff [owner] nor the Defendant [materialman] has complied with Section 713.06, F.S. The Defendant did not timely serve the preliminary notice upon the owner and the Plaintiff owner did not require from his Contractor a final payment affidavit. Consequently, both the Plaintiff and the Defendant have called upon able counsel to extricate them from their respective predicaments.

In the leading case of Crane Co. v. Fine, 221 So. 2d 145 (Fla.1969), the Florida Supreme Court held that while a notice to the owner given in compliance with the time limitations provided in Section 713-06(2)(a) placed the lienor in a priority position, such a notice given after the expiration of the 45-day period could be the basis for perfecting a valid lien provided such notice was given within the requisite 90-day period and before the owner has properly paid that portion of the sums due under the direct contract to which such lienor would be entitled. 1800 North Federal Corporation v. Westinghouse Electric Supply Company, 224 So. 2d 384 (4th DCA 1969); Moretrench Corporation v. Bronson & Veal Enterprises, Inc., 262 So. 2d 206 (4th DCA Fla. 1972); Warren v. Bill Ray Construction Co., Inc., 269 So. 2d 25 (3rd DCA Fla. 1972).

In the last cited case of Warren v. Bill Ray Construction Co., Inc., supra, 269 So. 2d 25 at page 27 the District Court states:

“That delay in furnishing the preliminary notice did not vitiate the lien, but could affect the amount of recovery thereon. This is so because failure to file the preliminary notice within 45 days after the commencement date would operate to deprive the lienor of the priority which timely filing thereof would have assured, but the lien would be effective for recovery by the lienor (pro rata with others similarly situated) out of funds represented by progress payments or final payment not made prior to the filing of the preliminary notice (or which were not properly paid under the lien law. Section 713.06(3) Fla.Stat., F.S.A.) See Crane Co. v. Fine, Fla.1969, 221 So. 2d 145, 153.” (Emphasis supplied)

In the case of Moretrench Corporation v. Bronson & Veal Enterprises, Inc., supra, 262 So. 2d 206, at page 207, the Fourth District Court of Appeal stated as follows:

“If funds remained available after all lien-holders filing timely notice had been discharged, then the tardy lien-holder could also receive payment.”

In the instant case, the Plaintiff did not comply with Section 713.06(3)(d)(5), Florida Statutes, which requires that the owner shall retain the last payment due under a contract or ten per cent (10%) of the original contract price, whichever is larger, and further requires that said sum shall not be dispersed until the Contractor’s affidavit required under Section 713.06(3)(d)(l), Florida Statutes, has been delivered to the owner. Section 713.06(3)(d)(6), Florida Statutes, provides that failure of the owner to comply with Section 713.06(3)(d)(5), supra, renders his property subject to the full amount of valid liens.

However, Section 713.06(3)(d)(6)(h), Florida Statutes, specifically limits the liability of the owner’s property only to the extent of retentions and improper payments.

The contract price was $25,164.46 and the last payment was to be twenty per cent (20%) of such amount or $5,032.89. Under Section 713.06(3)(d)(5), supra, the amount of $5,032.89 should have been withheld by the Plaintiff owner until he received the final payment affidavit of the Contractor. An owner can rely fully upon such an affidavit from the Contractor to the extent that it states there are no sums due any materialman or subcontractor and to the extent the Contractor has not received any notice of any lien claim. Crane Co. v. Fine, supra, 221 So. 2d 145, at page 153.

In the instant case, the plaintiff owner only retained the sum of $1,164.64 and which sum the Defendant received, but the Plaintiff owner improperly paid without having required a contractor’s final payment affidavit the sum of $3,868.43 (the difference between the amount that should have been retained and the actual amount retained by the Plaintiff).

Consequently, the Court finds Plaintiff is liable to the Defendant only for the sum of $3,868.43.

The Plaintiff argues rather persuasively that the Defendant did not give the preliminary notice to the Plaintiff owner béfore filing its claim of lien and therefore its lien is invalid. In the instant case, the notice was served by mail shortly prior to the filing of the claim of lien. However, no notice is required for the lienor to share in the final payment as set forth in Crane Co. v. Fine, supra, 221 So. 2d 145, at pages 150-153.

Accordingly, the opinion of the Fourth District Court of Appeal is quashed and the cause .remanded for further proceedings consistent with this opinion.

It is so ordered.

ADKINS, ENGLAND, SUNDBERG and KARL, JJ., concur. OVERTON, C. J., and BOYD, J., dissent.

ORDER

Counsel for Respondent having filed in this cause petition for rehearing, and it having been considered, it is ordered that the petition for rehearing is visited to the revised opinion and said petition is hereby denied.

OVERTON, C. J., and ADKINS, ENGLAND, SUNDBERG, HATCHETT and KARL, JJ., concur. BOYD, J., dissents.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • Tuttle/White Constructors, Inc. v. Hughes Supply, Inc., 371 So. 2d 559 (Fla. 4th DCA 1979)
    …v. Albert & Jamerson Bldg. Supply Corp., 212 So. 2d 13 (Fla. 4th DCA 1968). [*562] However, the failure of a prospective lienor to file notice to owner within forty-five days does not act as an absolute bar to recovery. Konsler Steel Co. v. Partin, 356 So. 2d 264 (Fla.1978); Moretrench Corp. v. Bronson & Veal Enterprises, Inc., 262 So. 2d 206 (Fla. 4th DCA 1972). The case of Crane Co. v. Fine, 221 So. 2d 145 (Fla.1969), recognized the right of a supplier of services or materials to proceed to establish an eq…
  • Royal v. Clemons, 394 So. 2d 155 (Fla. 4th DCA 1981)
    …ed to former Section 713.-06(2)(a), Florida Statutes (1977).2 Under this statute, late notice to owner merely affects one’s status as a priority lienor. We must adhere to the pronouncement of the Florida Supreme Court in Konsler Steel Co. v. Partin, 356 So. 2d 264 (Fla.1978), wherein it stated: In the leading case of Crane Co. v. Fine, 221 So. 2d 145 (Fla.1969), the Florida Supreme Court held that while a notice to the owner given in compliance with the time limitations provided in Section 713.-06(2)(a) plac…
  • Combs v. ST. Joe Papermakers Fed. Credit Union, 383 So. 2d 298 (Fla. 1st DCA 1980)
    …n equitable lien on unpaid funds or improperly paid funds despite his failure to perfect a mechanic’s lien. Morgan v. Goodwin, 355 So. 2d 217 (Fla. 1st DCA 1978); Crane Company v. Fine, 221 So. 2d 145 (Fla.1969); and Konsler Steel Company v. Partin, 356 So. 2d 264 (Fla.1978). However, the pleadings below did not pray for an equitable lien. An appellant cannot raise a point for the first time on appeal. Likewise, an appellate court is not at liberty to grant a remedy not sought in the trial court. The Cabinet…

Previewing 3 of 5 citing cases — full citator treatment, depth of discussion, and citing context are member features.

Join FLexlaw to unlock all legal intelligence

Authorities Cited

Full citator, related cases, and AI research tools

Open in FLexlaw