BISHOP SIGNS, INC., APPELLANT/CROSS APPELLEE,
v.
PETER MAGEE, JOHN MAHON D/B/A P.J. CAVANAUGH'S RESTAURANT, APPELLEES/CROSS APPELLANTS

Fla. 4th DCA | 1986-10-01
No. 85-2134
GUNTHER, J., and POLEN, MARK, Associate Judge, concur.
494 So. 2d 532 Florida District Court of Appeal, Fourth District (1986) Positive Treatment
Cited by 6 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.


Holding

The court held that a contractor's failure to serve the statutory affidavit is a bar to a mechanic's lien foreclosure action, and the contractor's allegations did not excuse this failure.


Headnotes

[1] The filing of a contractor's affidavit is a condition precedent to the maintenance of an action to foreclose a mechanic's lien.

[2] Failure to serve a contractor's affidavit at least five days before instituting an action to enforce a mechanic's lien bars the action unless compliance can be excused by…

Previewing 2 of 4 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

A sign contractor failed to serve a required contractor's affidavit before filing a mechanic's lien foreclosure suit. The trial court dismissed the am…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
STONE, Judge.

STONE, Judge.

The appellant-sign contractor failed to serve a contractor’s affidavit prior to suit as required for the foreclosure of a mechanic’s lien by section 713.06(3)(d)l, Florida Statutes (1985). That section provides:

The contractor shall have no lien or right of action against the owner for labor, services, or materials furnished under the direct contract while in default for not giving the owner the affidavit. The contractor shall execute the affidavit and deliver it to the owner at least 5 days before instituting an action as a prerequisite to the institution of any action to enforce his lien under this chapter, even if the final payment has not become due because the contract is terminated for a reason other than completion and regardless of whether the contractor has any lienors working under him or not.

The trial court, having previously dismissed the complaint with leave to amend, granted a motion to dismiss the amended complaint with prejudice.

Appellant concedes the failure to comply with the statute, but claims that its un-sworn allegation in the amended complaint, stating that there were no subcontractors involved, and that the contract called for Bishop Signs to supply the labor and material, excuses its lack of compliance with the mechanic’s lien law. Bishop Signs, Inc. is a contractor within the definition of section 713.01(2), Florida Statutes (1985).

Appellant also seeks, in the alternative, that we remand this cause so that it would have the opportunity to file an affidavit at this time. Appellee has cross-appealed, contending that the court erred in finding that their title had not been slandered by the filing of the unexecuted and unverified claim of lien.

The filing of a contractor’s affidavit is a condition precedent to the maintenance of an action to foreclose a mechanic’s lien. Failure to serve the affidavit is generally a bar to such an action. See Leader Mortgage Co. v. Rickards Electric Service, Inc., 348 So. 2d 1202 (Fla. 4th DCA 1977); Sowers v. Hoenstine, 417 So. 2d 1137 (Fla. 5th DCA 1982); Mardan Kitchen Cabinets, Inc. v. Bruns, 312 So. 2d 769 (Fla. 3d DCA 1975). Failure to comply with the statute will result in dismissal of the foreclosure unless the lienor is able to excuse compliance under circumstances that obviate the requirement of strict compliance. See Atlantic Gardens Landscaping, Inc. v. Boca Raton Land Development, Inc., 360 So. 2d 1278 (Fla. 4th DCA 1978); McMahan Construction Co., Inc. v. Carol’s Care Center, Inc., 460 So. 2d 1001 (Fla. 5th DCA 1984); Brown v. First Federal Savings & Loan Association of New Smyrna, 160 So. 2d 556 (Fla. 1st DCA 1964). Appellant here fails to allege facts constituting such an exception.

Appellant relies on Orange Plumbing & Heating Co. v. Wolfe, 89 So. 2d 671 (Fla.1956), and Brown. However, Brown itself sets the standard by which the appellant’s contention fails:

[Dismissal is proper unless the complaint shows that the sworn statement was furnished or alleges facts clearly avoiding the necessity to furnish it, and the circumstances peculiar to each case govern. Where the facts are such that any doubt exists as to whether the sworn statement is required, the issue should be resolved in favor of strict compliance with the statutory requirement because, first, the Mechanics’ Lien Law affords the lienor a right not accorded by the common law, and secondly, the statutory sworn statement was designed to protect the property owner against very real dangers inherent in the creation of the lien upon his property.

Id. at 561. Appellant argues that this is not a large project. However, the size of the project is not a significant consideration to the Brown exception. The applicable concern should be whether it is the type of contract which, by its nature, does not entail the services of subcontractors or the furnishing of labor or material by others. See Brown at 561 and 563.

This case has been pending since the summer of 1981. There is no contention that appellant has ever sought leave to amend to further excuse compliance with the statute, or that it has ever sought to tender an affidavit prior to this appeal. Therefore, McMahan Construction Co. v. Carol’s Care Center, Inc., relied upon by appellant, is inapplicable.

There is no single test to determine the precise contents of a complaint which will satisfy the exception to the rule. In Smyler v. Katzen, 289 So. 2d 477 (Fla. 3d DCA 1974), the court was of the view that there were sufficient allegations in the complaint to meet the test. Here, there are not, as the contract is of the type that might involve others in its performance. See Sowers v. Hoenstine. Here, not only is it arguable that work and materials could be furnished by other subcontractors or laborers, but such may even have been contemplated with respect to at least the electrical portion of the job. We conclude that the owner under these facts is entitled to the protection afforded by the statute and that there was no error in dismissing the complaint. With respect to the cross appeal, Bishop has failed to provide us with an adequate record from which to grant the relief requested. Applegate v. Barnett Bank of Tallahassee, 377 So. 2d 1150 (Fla.1979); Kauffmann v. Baker, 392 So. 2d 13 (Fla. 4th DCA 1980).

We therefore affirm the judgment of the trial court.

GUNTHER, J., and POLEN, MARK, Associate Judge, concur.


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • City OF Coconut Creek v. City OF Deerfield Beach, 840 So. 2d 389 (Fla. 4th DCA 2003)
    …ired); Privas v. Brisson Custom Homes, Inc., 817 So. 2d 983, 984-85 (Fla. 4th DCA 2002) (reversing judgment foreclosing lien where final contractor’s affidavit not timely served on homeowner within statutory time limit); Bishop Signs, Inc. v. Magee, 494 So. 2d 532, 533-34 (Fla. 4th DCA 1986) (upholding dismissal with prejudice where contractor failed to deliver final contractor’s affidavit five days prior to suit); Veal v. Escambia County, 773 So. 2d 625, 625-26 (Fla. 1st DCA 2000) (finding a failure to compl…
  • Timbercraft Enters., Inc. v. Adams, 563 So. 2d 1090 (Fla. 4th DCA 1990)
    …he marl delivered to the Adamses’ property was purchased from a supplier. Timbercraft’s speculation that the marl supplier would not have liened the Adamses property falls short of the standard set forth by this court in Bishop Signs, Inc. v. Magee, 494 So. 2d 532 (Fla. 4th DCA 1986), for excusing noncompliance with the statutorily mandated serving of the contractor’s affidavit. In Bishop Signs, this court noted that the filing of a contractor’s affidavit is a condition precedent to the maintenance of a mech…
  • Puya v. Superior Pools, 902 So. 2d 973 (Fla. 4th DCA 2005)
    …or fails to timely furnish a final payment affidavit, the owner is generally entitled to dismissal of the contractor’s foreclosure suit. See Privas v. Brisson Custom, Homes, Inc., 817 So. 2d 983, 984 (Fla. 4th DCA 2002); Bishop Signs, Inc. v. Magee, 494 So. 2d 532, 533 (Fla. 4th DCA 1986); Paulk v. Peyton, 648 So. 2d 772, 773 (Fla. 1st DCA 1994). Section 713.06(3)(c)5., makes the requirements of section 713.06(3)(d)l. applicable to this case. Section 713.06(3)(c)5. provides that even “[i]f the contract is te…