YOUNG MANUFACTURING, INC., APPELLANT,
v.
ROBERT BROOKS, D/B/A HIZ AND MIZ AND HIZ AND MIZ SPORTSWEAR AND MIZ TENNIS CREATIONS, INC., D/B/A HIZ AND MIZ AND HIZ & MIZ SPORTSWEAR, APPELLEES; ROBERT BROOKS, D/B/A HIZ AND MIZ AND HIZ AND MIZ SPORTSWEAR AND MIZ TENNIS CREATIONS, INC., D/B/A HIZ AND MIZ AND HIZ & MIZ SPORTSWEAR, APPELLANTS, V. YOUNG MANUFACTURING, INC., APPELLEE

Fla. 3d DCA | 1989-05-16
Nos. 88-2000, 88-2458
Before BARKDULL' and BASKIN, JJ., and JOSEPH P. McNULTY, Associate Judge.
543 So. 2d 388 Florida District Court of Appeal, Third District (1989) Positive Treatment
Cited by 5 cases

AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.

Synopsis

Young Manufacturing, Inc. appealed the trial court's erroneous calculation of pre-judgment interest in a breach of contract action. The appellate court reversed the interest calculation, holding that pre-judgment interest must be awarded on the full damages from the breach date through settlement, and then on remaining amounts through judgment, to make the plaintiff whole.


Holding

Pre-judgment interest must be awarded on the total damages ($7,169.85) from the breach date (August 13, 1979) to the settlement date (January 23, 1986), with that accrued interest added to principal before deducting the settlement payment. Additionally, pre-judgment interest is owed on the remaining amount due after settlement from the settlement date through judgment.


Headnotes

[1] Pre-judgment interest is to make an aggrieved plaintiff whole from the date of loss, contemplating the time value of money due but unpaid until liquidated at trial.

[2] A settlement payment from one co-defendant should not reduce the pre-judgment interest awarded to a plaintiff on the total damages found due.

Previewing 2 of 5 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.

Join FLexlaw to unlock all legal intelligence

Key Quotes

“It is now settled that pre-judgment interest is to make the aggrieved plaintiff "whole" from the date of the loss which, in the case of unliquidated damages, necessarily must contemplate the time value of monies due but unpaid until liquidated at trial.”

Establishes the fundamental purpose of pre-judgment interest and its application to unliquidated damages.

Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.

Join FLexlaw to unlock all legal intelligence

Facts & Procedural History

The trial court found total damages of $7,169.85 resulting from breach of contract. A co-defendant settled for $5,000.00 approximately four weeks befo…

The full statement of facts, procedural history, and disposition for this case are member content.

Join FLexlaw to unlock all legal intelligence

© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.


Opinion of the Court
PER CURIAM.

PER CURIAM.

We conclude this day that the trial court erroneously miscalculated pre-judgment interest awarded to plaintiff/appellant, Young Manufacturing, Inc., in this breach of contract action. We reverse only that aspect of the appeal/cross-appeal herein.

In a joint and several final judgment entered after a non-jury trial on February 19,1986, the trial court found that the total amount of damages suffered by Young because of the breach of contract was $7,169.85. The parties previously having stipulated that approximately four weeks prior to the entry of the judgment one co-defendant “settled” his obligation to Young in the premises for a payment of $5,000.00, the trial court reduced the total damages payable to Young by the amount of the settlement. Thereupon, judgment was entered for a net sum of $2,169.85 in damages due Young from the remaining defendants. The court also reserved jurisdiction to award pre-judgment interest, but in a post-judgment order the court denied such interest in any amount.

This court subsequently affirmed the judgment generally, but expressly reversed the denial of pre-judgment interest. Young Manufacturing, Inc. v. Brooks, 507 So. 2d 722 (Fla. 3d DCA 1987).

On remand, the trial court calculated pre-judgment interest only on the $2,169.85 remaining on the amount of damages found due, the net result of which was that no pre-judgment interest at all was awarded on the first $5,000.00 of the total damages due. This was error. It is now settled that pre-judgment interest is to make the aggrieved plaintiff “whole” from the date of the loss which, in the case of unliquidated damages, necessarily must contemplate the time value of monies due but unpaid until liquidated at trial. Argonaut Insurance Co. v. May Plumbing Co., 474 So. 2d 212 (Fla.1985).

Young’s damages resulting from the breach of contract here, as found by the trial court, were $7,169.85. It was thus entitled, first, to interest on this amount from the date of the breach (August 13, 1979) to the date of the settlement with the co-defendant (January 23, 1986), which, as of that date, should have been added to the principal amount then due. The $5,000.00 settlement should then have been deducted from this new total and not only from the $7,169.85 principal, which was what was done by the judgment ultimately entered herein for $2,169.85. This ought not to be altered simply because the co-defendant settled for a part of the full amount due, nor because the settlement may have been credited in whole or in part to principle1 and we would agree with the Massachusetts Court that “a plaintiff ought not to receive a lesser judgment (i.e. damages, interest and costs) because one among multiple [defendants] has settled in good faith.” Harvey Essex Bancorp, Inc., 25 Mass.App.Ct. 323, 517 N.E. 2d 323 (1988).

See also Boston Edison Co. v. Tritsch, 370 Mass. 260, 346 N.E. 2d 901 (1976).

This rationale, indeed, was indulged in by our sister court, in calculating costs, in Publix Super Markets, Inc. v. Moton, 433 So. 2d 71 (Fla. 2d DCA 1983).

Secondly, Young is entitled to pre-judgment interest on the remaining amount due after the settlement, including both principal and interest then remaining unpaid, from and after the date of the settlement to the date of the judgment. Again, Young must be made “whole.”

In view whereof, we reverse and remand for recalculation of pre-judgment interest in accordance with the foregoing. In all other respects, the order appealed and cross-appealed from is affirmed.

. Though the final judgment has been affirmed generally as noted, and is thus the law of the case, the crediting of the settlement payment only to the principal amount of damages found due, as set forth in the final judgment, would not preclude an award of pre-judgment interest, of itselfr to take into account and include all such interest payable so as to make Young "whole.”


Cases With Similar Vibessemantic neighbors from the corpus


Citator

Cited By

  • …yment on account he received to cover the time between the date on which the trial court found payment due, September 19, 1985, and the date on [*1189] which Underwriters made the payment, December 18, 1987. We agree. See Young Mfg., Inc. v. Brooks, 543 So. 2d 388 (Fla. 3d DCA 1989). Accordingly, as to the above matters only we reverse and remand, and otherwise affirm. GLICKSTEIN and POLEN, JJ., and DONNER, AMY STEELE, Associate Judge, concur.…
  • Vitt v. Rodriguez, 960 So. 2d 47 (Fla. 5th DCA 2007)
    …a.1849). Since then the courts of Florida have generally adhered to the rule as enunciated in Story and Hart. See, e.g., Joyner v. Bernard, 153 Fla. 372, 14 So. 2d 724, 725 (1943); Pearson v. Grice, 8 Fla. 214 (Fla.1858); Young Mfg., Inc. v. Brooks, 543 So. 2d 388 (Fla. 3d DCA 1989). In applying the common law rule to the case before us we conclude that the trial court erred in its ruling that Mr. Rodriguez’s past due payments would first be applied to principal, and then to interest. The payments made by Mr…
  • Overseas Private Inv. Corp. v. Metro. Dade Cnty., 1993 U.S. Dist. LEXIS 9823 (S.D. Fla. 1993)
    …rata by the amount of the settlement between Plaintiffs and Conservation District in accordance with Florida law. See Fla. Min. & Materials v. Van Antwerp, 601 So.2d 621 (Fla.App.Ct. 2nd Dist.1992); see also, Young Manuf. Inc. v. Brooks, 543 So.2d 388 (Fla.App. 3rd Dist.1989). Accordingly, judgment shall be entered in favor of Plaintiffs and against Dade County in the total amount of $6,675,000, which shall be set forth in a separate judgment pursuant to Fed.R.Civ.P. 58. Dade County’s motion…

Authorities Cited

Full citator, related cases, and AI research tools

Open in FLexlaw