JACKSONVILLE PORT AUTHORITY, CITY OF JACKSONVILLE, APPELLANT,
v.
W.R. JOHNSON ENTERPRISES, INC., D/B/A JOHNSON/AMERICAN, APPELLEE
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
Jacksonville Port Authority appeals a jury verdict finding it breached a contract with W.R. Johnson Enterprises to perform phase III installation work on a container crane repair project. The appellate court reverses, holding that no binding contract existed because the parties never achieved mutual agreement on essential terms, particularly price and scope of work.
The court reversed, holding that no enforceable contract existed between JPA and Johnson because the parties never achieved reciprocal assent to essential terms. Although a general understanding may have existed in April 1989, the scope of Phase III work was not presented until July 1989 and continued to be modified, and the parties never agreed on a definite price, with negotiations continuing as late as January 1990.
[1] A binding contract requires mutual assent to essential terms; if essential matters remain open for further consideration, no completed contract exists.
[2] The failure to sufficiently determine quality, quantity, or price may preclude the finding of an enforceable agreement.
Previewing 2 of 5 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.
Join FLexlaw to unlock all legal intelligence“While it is not necessary that all details of an agreement be fixed in order to have a binding agreement between parties, if there has been no agreement as to essential terms, an enforceable contract does not exist.”
Establishes the legal standard that essential terms must be agreed upon for contract formation
Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.
Join FLexlaw to unlock all legal intelligenceJPA authorized an emergency crane repair project divided into three phases. JPA established relationships with three companies: Alliance Machinery Com…
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Partial Performance Doctrine cases and more on FLexlaw
WOLF, Judge.
Jacksonville Port Authority (JPA) challenges a final judgment based on a jury verdict, finding that JPA breached its contract with W.R. Johnson Enterprises, Inc. (appellee). JPA asserts a number of issues on appeal, one of which we find dispositive: whether the trial court erred in failing to grant JPA’s motion for directed verdict where the evidence failed to demonstrate mutual agreement on essential elements of the purported agreement. We find merit as to this point and reverse.
The dispute arises in connection with a project to inspect and repair one of JPA’s container cranes used to off-load ships.
The project was considered to be an emergency and, thus, JPA did not go through a formal bidding process, but instead authorized its purchasing agents to spend up to $1,250,000 in order to complete the project. The fourteen-month project, begun in April 1989 and completed in June 1990, was to be done in three phases. Phase I involved a survey and field inspection of the crane and would involve preparation of the necessary specifications and estimates for the repair. Phase II involved the manufacture of the necessary new and replacement parts. Phase III involved installation of the new parts, some repainting, and certification of the crane (ultimately phase III also involved raising the crane 10 feet in order to accommodate large ships).
In April 1989, JPA established a relationship with three companies in order to complete the project. Alliance Machinery Company, the original equipment manufacturer, was involved with the engineering evaluation and design services. Dawe and Son, a heavy machinery specialty consulting firm, was to be responsible for project oversight and specialty advisory services. Johnson, a local, industrial machinery contractor, was to provide qualified tradesmen, tools, and equipment necessary for the crane survey and later, for the actual repairs.
It is undisputed that during the early stages of the project, all the parties expected appellee to perform the phase I inspection and phase III installation work. Appellee asserts that in light of the general understanding and discussions of the parties as well as JPA budgeting $1,250,000 for completion of all three phases of the project, there was a binding agreement between JPA and appellee in April of 1989. This assertion is not consistent with the evidence presented.
On May 22, 1989, JPA asked that each contractor submit written proposals for the “work that can reasonably be estimated at this time.” Written proposals were submitted by all, and services purchase orders (SPO’s) were issued by JPA to begin the project. Johnson submitted written “specifications and estimates” for the field inspection or phase I of the project. Johnson’s proposal to do phase I for $219,450 was accepted by JPA when JPA issued SPO number 015 requiring Johnson to “provide all labor, materials and equipment necessary to perform the crane conditions survey of the Alliance crane in conjunction with direction from Alliance Machine Company and Dawe & Sons, per the attached proposal.” SPO number 015 specified the price as $219,450.
All parties agree that these actions were consistent with the practice of JPA during this project which was not to specifically formalize the relationship through contract, but rather to proceed through SPO’s.
Whether or not to proceed with phases II and III and the scope of the work involved in these phases depended on the results of the phase I inspection. Near the end of phase I, Alliance Machine Company found that the crane appeared sound and “worthy of the requested modifications.”
JPA made the decision to proceed with the project and issued SPO numbers 033 and 050 to Alliance Machine Company in response to their written proposals. SPO number 033 on August 11, 1989, authorized Alliance to work on major components, including the main hoist, for $314,725, and SPO number 050 on October 10,1989, authorized Alliance to work on other components for $285,870. Phase II included some repairs necessarily performed on the crane itself, and appellee was responsible for these field repairs.
In late July and August of 1989, the first estimates of the scope of the work involved in phase III were presented. At that time, appellee informed JPA of the cost of proceeding with phase III. On August 31, Ernest Dawe, the project manager, estimated that the cost of appellee’s installation work would be $103,450. Evidently, additional work was added to the project. On November 2, 1989, appellee sent a letter to Mr. Dawe stating that recently received engineering information from Alliance Machine Company would require a reassessment of Johnson’s proposed costs to do the phase III work. On November 27, 1989, Johnson sent to the Project Manager Dawe a detailed cost breakdown for portions of the work to be done and stated that “our last quotation offered was in error.”
On January 16,1990, Johnson sent another letter, this one to JPA’s engineering director, stating that the earlier cost estimates for phase III work were founded on incomplete information, and the costs would be reesti-mated “in the next couple of days.” Johnson’s updated proposal for phase III work was a total price of $163,667. This offer was submitted January 18, 1990. The proposed price was higher than the $103,450 estimated in August, and JPA asked Johnson to reevaluate the proposal. In response, Johnson sent a letter on February 12, 1990, again to JPA’s engineering director, expressing the hope that their reduced price of $139,117, plus some additional fees, would be accepted.
In the meantime, JPA’s engineering director asked United Construction Services, Inc. to estimate and bid on phase III machine installation. On January 31, 1990, United Construction Services, Inc. quoted a price of $110,000 for the same services Johnson had bid for $163,667. United Construction Services, Inc. had already bid $171,900 for the work to raise the crane 10 feet. On February 22, 1990, JPA issued SPO number 077 to United Construction for both the raising of the crane and the phase III machine installation work originally intended for Johnson. Appellee claimed JPA breached their agreement by awarding the phase III work to another contractor. While it is not necessary that all details of an agreement be fixed in order to have a binding agreement between parties, if there has been no agreement as to essential terms, an enforceable contract does not exist. Williams v. Ingram, 605 So. 2d 890, 893 (Fla. 1st DCA1992); Blackhawk Heating and Plumbing Co., Inc. v. Data Lease Financial Carp., 302 So. 2d 404 (Fla.1974).
So long as any essential matters remain open for further consideration, there is no completed contract. In order to create a contract it is essential that there be reciprocal assent to a certain and definite proposition.
Mann v. Thompson, 100 So. 2d 634, 637 (Fla. 1st DCA1958). Failure to sufficiently determine quality, quantity, or price may preclude the finding of an enforceable agreement. See Blackhawk Heating and Plumbing Co., Inc. at 408, citing Truly Nolen, Inc. v. Atlas Moving and Storage Warehouse, Inc., 125 So. 2d 903 (Fla. 3d DCA1961), cert. discharged, 137 So. 2d 568 (Fla.1962).
Where the parties are continuing to negotiate as to these essential terms, there can be no meeting of the minds. Central Properties, Inc. v. William H. Robbinson, 450 So. 2d 277, 280 (Fla. 1st DCA 1984), modified, 468 So. 2d 986 (Fla.1985).
In the instant case, while a general understanding may have existed in April of 1989 concerning appellees’ continued participation as to phase III of the project, clearly no enforceable contract existed. The scope of the work contemplated in phase III was not presented until late July of 1989. Additions continued to be made after that time. There was never an agreed-upon price between the parties. Correspondence between the parties indicated that negotiations between the parties as to these essential terms were continuing as. late as January 1990. Letters and correspondence from appellee confirm that it still felt that it had not been awarded these projects, but was still seeking acceptance of its proposals. Under these circumstances, no binding agreement existed between the parties. We, therefore, reverse that portion of the judgment awarding damages against JPA for breach of contract.1
SMITH and MICKLE, JJ., concur. . While Johnson also asserts that a contract was created as a result of partial performance, these allegations have greater weight in cases involving defining vague terms within a contractual relationship which is found to have existed, in pursuance of damages involving a claim under quan-turn merit or in removing an oral agreement from the prohibition of the statute of frauds. Blackhawk, 302 So. 2d at 408, 409, and Poinciana Properties Ltd. v. Englander, 437 So. 2d 214 (Fla. 4th DCA1983); rev. denied, 447 So. 2d 887 (Fla.1984).
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By (16 total)
-
W.R. Townsend Contracting, Inc. v. Jensen Civil Constr., Inc., 728 So. 2d 297 (Fla. 1st DCA 1999)…, a plaintiff is required to allege facts that, if taken as true, demonstrate that the parties mutually assented to “a certain and definite proposition” and left no essential terms open. Jacksonville Port Authority v. W.R. Johnson Enterprises, Inc., 624 So. 2d 313 (Fla. 1st DCA 1993) (evidence did not establish existence of binding agreement between port authority and machinery contractor for installation of machinery even though parties initially agreed that contractor was to perform initial work as well as…
-
B. Freeman Irby, M.D. v. Mem'l Healthcare Grp., Inc., 901 So. 2d 305 (Fla. 1st DCA 2005)…one construction, an issue of fact is created which cannot be resolved by summary judgment. We cannot agree with either argument. As this court explained in Jacksonville Port Authority, City of Jacksonville v. [*306] W.R. Johnson Enterprises, Inc., 624 So. 2d 313, 315 (Fla. 1st DCA 1993): While it is not necessary that all details of an agreement be fixed in order to have a binding agreement between parties, if there has been no agreement as to essential terms, an enforceable contract does not exist. “So lo…
-
John Alden Life Ins. Co. v. Benefits Mgmt. Assocs., Inc., 675 So. 2d 188 (Fla. 3d DCA 1996)…ctual provision was merely an “agreement to agree” in the future about the bonus and hence unenforceable as a matter of law. Suggs v. Defranco’s, Inc., 626 So. 2d 1100, 1101 (Fla. 1st DCA 1993); Jacksonville Port Auth. v. W.R. Johnson Enters., Inc., 624 So. 2d 313, 315 (Fla. 1st DCA 1993), rev. denied, 634 So. 2d 629 (Fla.1994); Bee Line Air Transp. Inc. v. Dodd, 496 So. 2d 874 (Fla. 3d DCA 1986), rev. denied, 506 So. 2d 1040 (Fla.1987); see also Metropolitan Dade County v. Estate of Hernandez, 591 So. 2d 112…
Previewing 3 of 16 citing cases — full citator treatment, depth of discussion, and citing context are member features.
Join FLexlaw to unlock all legal intelligenceAuthorities Cited
- Blackhawk Heating & Plumbing Co., Inc. v. Data Lease Fin. Corp., 302 So. 2d 404 (Fla. 1974)
- Williams v. Ingram, 605 So. 2d 890 (Fla. 1st DCA 1992)
- Mann v. Thompson, 100 So. 2d 634 (Fla. 1st DCA 1958)
- Schwartz v. Zenia Schwartz, 450 So. 2d 277 (Fla. 3d DCA 1984)
- Robbinson v. Delk, 468 So. 2d 986 (Fla. 1985)
- Truly Nolen, Inc. v. Atlas Moving & Storage Warehouses, Inc., 125 So. 2d 903 (Fla. 3d DCA 1961)
- Atlas Moving & Storage Warehouses, Inc. v. Truly Nolen, Inc., 137 So. 2d 568 (Fla. 1962)
- Poinciana Props., Ltd. v. Englander Triangle, Inc., 437 So. 2d 214 (Fla. 4th DCA 1983)