CHOCTAWHATCHEE ELECTRIC COOPERATIVE, INC., APPELLANT,
v.
JAMES E. MOORE AND WIFE, BARBARA H. MOORE, APPELLEES
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
In this inverse condemnation case on second appeal, the court affirmed the trial court's determination that Choctawhatchee Electric Cooperative held an eight-foot-wide easement over the Moores' land. The court applied the principle that the burden on the servient estate must not exceed what is reasonably necessary and contemplated at the time the easement was acquired.
The court affirmed the trial court's final decree establishing an eight-foot-wide easement. The evidence was sufficient to permit the inferences drawn by the trial court, and the court could not find that the trial judge abused his discretion in entering the decree.
“whether the easement is acquired by user, express grant, dedication or by implication, the burden of a right of way upon the servient estate must not be increased to greater extent than reasonably necessary and contemplated at the time of initial acquisition”
Establishes the governing standard for determining the width of an easement, drawn from Crutchfield and applied as a guideline to the trial court
Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.
Join FLexlaw to unlock all legal intelligenceChoctawhatchee Electric Cooperative claimed an easement across the Moores' property. In the first appeal, the appellate court reversed a summary judgm…
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Inverse Condemnation cases and more on FLexlaw
The defendant in an inverse condemnation action has appealed from a final decree entered by the Circuit Court for Oka-loosa County, holding that the defendant held an easement eight feet wide over the plaintiffs’ land. This is the second appearance of this cause in this court—see Moore v. Choctawhatchee Electric Co-operative, Inc., 196 So.2d 788 (Fla.App.1967).
The basic question presented for our determination in the present appeal is whether the said court abused its discretion in entering the said final decree, in the light of the evidence before that court.
In the first appeal, as reported in 196 So.2d 788 (1967), we considered an order entered by the Circuit Court granting the defendant’s motion for a summary judgment. We reversed in part the said order, stating that we were of the opinion that a genuine issue of a material fact (the width of the easement) existed, precluding the entry of a summary judgment.
In the only footnote in our opinion in the first appeal (196 So.2d at page 789) we summarized with obvious approval the holding of the Florida Supreme Court in Crutchfield v. F. A. Sebring Realty Co., 69 So.2d 328 (1954), that “whether the easement is acquired by user, express grant, dedication or by implication, the burden of a right of way upon the servient estate must not be increased to greater extent than reasonably necessary and contemplated at the time of initial acquisition.” By using the quoted language, we intended, of course, that that language serve as a guideline to the Circuit Court, upon remand of the cause, in determining the question of the width of the easement.
After remand of the cause, two hearings were held at which the evidence of the parties was taken. The court then entered the final decree appealed from herein.
In the first appeal of this cause we recognized that the defendant had a right to an easement across the plaintiffs’ land. Therefore, in this second appeal, the entitlement of the said easement is settled' by “the law of the case,” and the only question before us in this second appeal is the width of that easement. More precisely, the question is whether the evidence, adduced by the parties at the two hearings held after the remand of the cause following the first appeal, is sufficient to support the finding of the chancellor that an eight-foot easement is “reasonably necessary and contemplated at the time of initial acquisition” (quoting the guideline in our opinion in the first appeal).
At the two hearings following the said remand, at which the Circuit Court *22sat as the Chancellor trying the facts, the parties presented their testimony and other evidence relative to the question of the width of the easement in the light of the above guideline. Little evidence was adduced as to a reasonably necessary width and as to the width contemplated at the time of the initial acquisition. We have examined the evidence taken at the two hearings and find such evidence to he sufficient to permit the inferences drawn by the chancellor and his finding! that an easement eight feet wide is appropriate under the guideline we furnished him in the first appeal. In addition, the final decree appealed from herein comes to us with the presumption of correctness. We cannot find that he has abused his judicial discretion in entering that decree.
Therefore, the said final decree must be and it is
Affirmed.
RAWLS and JOHNSON, JJ., concur.
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By
-
Blowers v. Williams, 360 So. 2d 1293 (Fla. 1st DCA 1978)…hough neither the trial court’s judgment nor this one should be read as authorizing appellee to pave or otherwise improve the easement way in a manner detrimental to appellant’s adjacent grove. See Choctawhatchee Electric Cooperative, Inc. v. Moore, 220 So. 2d 20 (Fla. 1st DCA 1969); Corrigans v. Sebastian River Drainage District, 223 So. 2d 57 (Fla. 4th DCA 1969). AFFIRMED. BOYER, Acting C. J., and BOOTH, J., concur.…
-
State of Fla. Dep't OF Transp. v. Fla. E. Coast Ry. Co., 275 So. 2d 289 (Fla. 3d DCA 1973)…hoose not to reconsider the matters. See: Utley v. City of St. Petersburg, 121 Fla. 268, 163 So. 523; McGregor v. Provident Trust Co. of Philadelphia, 119 Fla. 718, 162 So. 323; Cf., Choctawhatchee Electric Cooperative, Inc. v. Moore, Fla.App. 1969, 220 So. 2d 20. Moreover, we are of the opinion that there was substantial competent evidence before the trial judge to substantiate its finding that the day of taking was December 1, 1966. Thus, no reversible error has been made to appear in this regard. Appell…
-
Choctawhatchee Elec. Coop., Inc. v. Moore, 225 So. 2d 912 (Fla. 1969)…Certiorari denied without opinion. 220 So. 2d 20.…
Authorities Cited
- Crutchfield v. F. A. Sebring Realty Co., 69 So. 2d 328 (Fla. 1954)
- Moore v. Choctawhatchee Elec. Co-Operative, Inc., 196 So. 2d 788 (Fla. 1st DCA 1967)